   Weekly progress report as on 28.03.2014
    
PROGRESS OF ROB ALOOR-MALA  WORK AS ON 28-03-2014.
  Description Completed/ Progress Remarks
1 ROB ALOOR-MALA    
1 Piling Completed. completed 32/32
2 Pilecap In Progress COMPLETED 8OUT OF 8
3 Pier In Progress completed 6out of 6.
4 Piercap In Progress 6 nos completed out of 6.
5 Girder  started P1-P2,A1-P1 COMPLETED.P3-P4  GIRDERin progress.
6 Slab  started P1-P2  completed
7 Handrail with kerb Not started  
8 Ex.joint Not started  
9 Tarring work Not started  
10 Service road work(Diversion road)  In Progress aloor right side in progress 100% completed.Mala side LHS 100%
11 Retaining wall worK  started aloor side LHS WALL 90% COMPLETED   ,mala side WALL 50 M COMPLETED. 
12 Load test . Completed. In P4 location.
       
       
       
       
       
       
       
 