   17.12.2010
    
Progress Report For Parappanangadi ROB for the week ending on 17-12-2010
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  Remarks 
1 PILE CALICUT  SIDE 30 5 25 0 0 6 0 6  
2 PILE NH SIDE 33 30 3 0 0 0 0 3  
3 PILE RAILWAY SPAN 20 0 20 0 0 0 0 0  
4 PILE CAP CALICUT  SIDE 10 0 10 0 0 0 0 0  
5 PILE CAP NH SIDE 11 0 11 4 2 1 5 1  
6 PILE CAP RAILWAY SPAN 4 0 4 0 0 0 0 0  
7 PIER CALICUT  SIDE 10 0 10 0 0 0 0 0  
8 PIER NH SIDE 11 0 11 0 3 0 3 1  
9 PIER RAILWAY SPAN 4 0 4 0 0 0 0 0  
10 PIER CAP CALICUT  SIDE 10 0 10 0 0 0 0 0  
11 PIER CAP NH SIDE 11 0 11 0 0 0 0 2  
12 PIER CAP RAILWAY SPAN 4 0 4 0 0 0 0 0  
13 RE/R WALL CALICUT  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
14 RE/R WALL NH SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
16 BEAM/SLAB CALICUT  SIDE 10 0 10 0 0 0 0 0  
17 BEAM/SLAB NH SIDE 11 0 11 0 0 0 0 0  
18 BEAM/SLAB RAILWAY SPAN 3 0 3 0 0 0 0 0  
19 HR/FP/KERB CALICUT  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
20 HR/FP/KERB NH SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
21 HR/FP/KERB RAILWAY SPAN 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
22 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%   
 