   Weekly Progress Report as on 07.03.2014
    
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  Remarks 
1 PILE CHERUVATHOOR  SIDE 27 27 Completed  
2 PILE PADANNA SIDE 24 24 Completed  
3 PILE CAP CHERUVATHOOR SIDE 9 9 Completed  
4 PILE CAP  PADANNA SIDE 8 8 Completed  
5 PIER CHERUVATHOOR SIDE 9 9 Completed  
6 PIER PADANNA SIDE 8 8 Completed  
7 PIER CAP CHERUVATHOOR SIDE 9 9 Completed  
8 PIER CAP PADANNA SIDE 8 8 Completed  
9 RE/RC WALL CHERUVATHOOR  SIDE 100% 100% Completed  
10 RE/RC  WALL PADANNA SIDE 100% 100% Completed  
11 BEAM/SLAB CHERUVATHOOR  SIDE 9 8 1 RP3-P8 adjacent span girder concreted. RP3-P8 adjacent span girder concreted.
12 BEAM/SLAB PADANNA SIDE 8 7 1 complete except railway adjacent span RAILWAY WORK OBSTRUCTING THE START.
13 EXPANSION JOINT CHERUVATHUR SIDE 9 8 1 0 0 0 0 0 complete except P8
14 EXPANSION JOINT PADANNA SIDE 8 7 1 0 0 0 0 0 complete except P7
15 KERB CHERUVATHOOR  SIDE 100% 100.00% complete except railway adjacent span  
16 KERB PADANNA SIDE 100% 100% complete except railway adjacent span  
17 HANDRAIL CHERUVATHUR SIDE 100% 100% complete except railway adjacent span  
18 HANDRAIL PADANNA SIDE 100% 100% complete except railway adjacent span  
19 Painting 100% 100% Completed Painting complete except adjacent span.
17 BM/BC 100% 90% 10% 10% 0.00% 0.00% 0.00% 0.00% Bitumen works complete except Padanna side 4m road .
18 Others/Miscellaneous                 Drainage works complete for 150 m at chr side.
19 ROAD WORK GSB+WMM Work 100% complete  
20 Drainage Padanna side 100.00% 98.00% 2.00% 2.00% 2.00% 0.00% 2.00% 2.00% Drainage works 3m remaining.
                    DR Work complete for 4m service road and 7m road chr side.
21 RAILWAY PORTION  RP1-RP2 SPAN GIRDER AND SLAB CONCRETED.CENTRE SPAN GIRDER LAUNCHING TO BE DONE.
                    Hume pipe laying complete at chr side to drain off rain water
                     
                     
                     
  Availbility of Men                   
  Date 3/1/2014 3/2/2014 3/3/2014 3/4/2014 3/5/2014 3/6/2014 3/7/2014    
  No of labours 1 1 1 1 1 1 1    
                     
  Material Stocking Status Required Available Remarks            
  Coarse Aggreagate (m3) available              
  Fine Aggreagate(m3) available            
  Cement(bag) RMC           
  Steel(MT) 4 10            
 