SlNo
|
Activity -Description
|
Total Quantity
|
Cumulative progress up to previous week
(1)
|
Balance work
(2)
|
Cumulative delayin weeks after
Spplagmnt
(3)
|
Work planned during the week
(4)
|
Actual work done during the week
(5)
|
Short fall in the week
(6)
|
Work Planned for next week
(7)
|
Remarks
|
13
|
Friction slab towards pulikkakadavu side
|
128m
|
Reinforcement Work 25m
|
Friction slab
|
|
PCC for 128 m and Reinforcement
for 25m
|
PCC for 128 m and Reinforcement
for 25m
|
-
|
Concreting of Friction slab
|
|