   Weekly progress report as on 21.03.2014
    
PROGRESS OF ROB ALOOR-MALA  WORK AS ON 21-03-2014.
  Description Completed/ Progress Remarks
1 ROB ALOOR-MALA    
1 Piling Completed. completed 32/32
2 Pilecap In Progress COMPLETED 8OUT OF 8
3 Pier In Progress completed 6out of 6.
4 Piercap In Progress 6 nos completed out of 6.
5 Girder  started P1-P2,A1-P1 COMPLETED.P3-P4  GIRDERin progress.
6 Slab  started P1-P2 RFT STARTED
7 Handrail with kerb Not started  
8 Ex.joint Not started  
9 Tarring work Not started  
10 Service road work(Diversion road)  In Progress aloor right side in progress 100% completed.Mala side LHS 100%
11 Retaining wall worK  started aloor LEFT side  WALL and 116 m  ,mala side WALL 30 M COMPLETED. 
12 Load test . Completed. In P4 location.
       
       
       
       
       
       
       
 
Back
 
    
P1-P2 SLAB RFT WORKS STARTED

    
    
DECK SLAB SHUTTERING IN P1-P2

      
 

 

 

 

 

 

 

 