Description |
Unit |
Total Quantity |
Cumulative production up to last week |
Work planned for this week |
Actual work done for this week |
Balance quantity |
Quantity planned for next week |
Remarks |
Clearing and grubbing |
Ha |
3.9 |
2.21 |
0.05 |
0.05 |
0.00 |
0.05 |
|
Dismantlingof rubble masonry, |
Cum |
100 |
189.92 |
10.00 |
0.00 |
10.00 |
10.00 |
|
Dismantling of advertisement boards, sign boards |
Nos |
60 |
20 |
5.00 |
0.00 |
5.00 |
5.00 |
|
Dismantling of Reinforced cement concrete |
Cum |
40 |
40.83 |
2.50 |
3.00 |
-0.50 |
2.50 |
|
Dismantling of cement concrete |
Cum |
50 |
28.746 |
5.00 |
5.40 |
-0.40 |
5.00 |
|
Earthwork excavation including removal of unsuitable soil |
Cum |
30210 |
8897.57 |
450.00 |
400.00 |
50.00 |
450.00 |
|
Loosening, levelingand Compacting original ground |
Cum |
1240 |
607.31 |
50.00 |
154.00 |
-104.00 |
50.00 |
|
Construction of granular sub-base |
Cum |
8050 |
2179 |
50.00 |
136.00 |
-86.00 |
50.00 |
|
Wet mix macadam |
Cum |
6900 |
1198 |
55.00 |
108.00 |
-53.00 |
100.00 |
|
Primer coat |
Sqm |
24370 |
4000 |
|
0.00 |
0.00 |
1000.00 |
|
Random Rubble Masonry |
Cum |
210 |
37 |
15.00 |
3.50 |
11.50 |
5.00 |
|
Construction of embankment of approved materials deposited at site |
Cum |
3890 |
264.2 |
50.00 |
262.00 |
-212.00 |
100.00 |
|
plain concrete / reinforced concretefor sub-MORTH -M15 |
Cum |
1050 |
226.99 |
12.50 |
15.00 |
-2.50 |
12.50 |
|
Cement concrete for plain concrete / reinforced concrete MORTH -M25 grade |
Cum |
5070 |
1089.54 |
50.00 |
46.00 |
4.00 |
100.00 |
|
Supplying, fitting and placing HYSD bar reinforcement in sub-structure |
MT |
510 |
110.706 |
5.00 |
4.00 |
1.00 |
5.00 |
|