   17.12.2010
    

RBDCK Engineer-Shri Ajaykrishnan, Contact No. 9745319841

KITCO Engineer - Shri Binu Lazar, Contact No.9446278195

GPT Engineer - Shri Sunny Pulikal, Contact No.9388085153 

 

Progress Report For Palakkad Sultanpet ROB for the week ending on 17-12-2010

Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  Remarks 
1 PCC for RAFT PALAKKAD SIDE 1 0 1 0 0 0 0 0  
2 PCC for RAFT MOYAN SCHOOL SIDE 3 1 2 1 1 1 1 0  
4 RAFT PALAKKAD SIDE 1 0 1 0 0 0 0 0  
5 RAFT MOYAN SCHOOL SIDE 3 0 3 0 1 0 1 1  
7 PIER PALAKKAD SIDE 1 0 1 0 0 0 0 1  
8 PIER MOYAN SCHOOL SIDE 3 0 3 0 0 0 0 0  
10 PIER CAP PALAKKAD SIDE 1 0 1 9 0 0 0 0  
11 PIER CAP MOYAN SCHOOL SIDE 3 0 3 8 0 0 0 0  
13 RE/R WALL PALAKKAD  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
14 RE/R WALL MOYAN SCHOOL SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
16 BEAM/SLAB PALAKKAD  SIDE 2 0 2 0 0 0 0 0  
17 BEAM/SLAB MOYAN SCHOOL SIDE 4 0 4 0 0 0 1 0  
18 BEAM/SLAB RAILWAY SPAN 7 0 7 0 0 0 1 0  
19 HR/FP/KERB CALICUT  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
20 HR/FP/KERB NH SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
21 HR/FP/KERB RAILWAY SPAN 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
22 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%   
 