Prevoius Weekly Reports

   weekly progress as on 14.3.2014
    

 

Description Unit  Total Quantity Cumulative production up to last week Work planned for this week Actual work done for this week Balance quantity Quantity planned for next week
General Clearance              
Clearing and grubbing  Ha 3.9 2.16 0.05 0.00 0.05 0.05
Dismantlingof rubble masonry,   Cum 100 179.92 10.00 1.70 8.30 10.00
Dismantling of advertisement boards, sign boards   Nos 60 15 5.00 0.00 5.00 5.00
Dismantling of Reinforced cement concrete   Cum 40 38.33 2.50 3.00 -0.50 2.50
Dismantling of  cement concrete Cum 50 23.746 5.00 0.00 5.00 5.00
Earthwork excavation including removal of unsuitable soil  Cum 30210 8447.57 450.00 235.00 215.00 450.00
Road works-Pavement              
Loosening, levelingand Compacting original ground  Cum 1240 557.31 50.00 39.00 11.00 50.00
Construction of granular sub-base Cum 8050 2129 50.00 119.00 0.00 50.00
Wet mix macadam Cum 6900 1143 55.00 108.00 0.00 100.00
Primer coat Sqm 24370 4000   0.00 0.00 1000.00
Random Rubble Masonry Cum 210 22 15.00 23.50 0.00 5.00
Construction of embankment  of approved materials deposited at site  Cum 3890 214.2 50.00 220.00 0.00 100.00
plain concrete / reinforced concretefor sub-MORTH -M15 Cum 1050 214.49 12.50 8.90 3.60 12.50
Cement concrete for plain concrete / reinforced concrete MORTH -M25 grade  Cum 5070 1039.54 50.00 45.00 5.00 100.00
Supplying, fitting and placing HYSD bar reinforcement in sub-structure  MT 510 105.706 5.00 4.26 0.74 5.00
 