PROGRESS OF ROB ALOOR-MALA WORK AS ON 14-03-2014. |
|
Description |
Completed/ Progress |
Remarks |
1 |
ROB ALOOR-MALA |
|
|
1 |
Piling |
Completed. |
completed 32/32 |
2 |
Pilecap |
In Progress |
COMPLETED 8OUT OF 8 |
3 |
Pier |
In Progress |
completed 6out of 6. |
4 |
Piercap |
In Progress |
6 nos completed out of 6. |
5 |
Girder |
started |
P1-P2,A1-P1 COMPLETED.P3-P4 GIRDERin progress. |
6 |
Slab |
started |
P1-P2 WORK STARTED |
7 |
Handrail with kerb |
Not started |
|
8 |
Ex.joint |
Not started |
|
9 |
Tarring work |
Not started |
|
10 |
Service road work(Diversion road) |
In Progress |
aloor right side in progress 100% completed.Mala side LHS 100% |
11 |
Retaining wall worK |
started |
aloor LEFT side WALL and 116 m ,mala side WALL 30 M COMPLETED. |
12 |
Load test . |
Completed. |
In P4 location. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|