Prevoius Weekly Reports

   weekly progress as on 7.3.2014
    

 

Description Unit  Total Quantity Cumulative production up to last week Work planned for this week Actual work done for this week Quantity planned for next week
             
Clearing and grubbing  Ha 3.9 2.16 0.05 0.00 0.05
Cutting of trees, Nos    0   0.00  
a) Girth 300mm to 600 mm Nos  25 120 5.00 0.00  
Dismantlingof rubble masonry,   Cum 100 179.92 10.00 1.50 10.00
Dismantling of advertisement boards, sign boards   Nos 60 15 5.00 0.00 5.00
Dismantling of Reinforced cement concrete   Cum 40 38.33 2.50 0.00 2.50
Dismantling of  cement concrete Cum 50 23.746 5.00 0.00 5.00
Earthwork excavation including removal of unsuitable soil  Cum 30210 8447.57 450.00 396.72 450.00
Loosening, levelingand Compacting original ground  Cum 5290 968.9   172.00  
Construction of sub grade  Cum 8050 2129 50.00 0.00 50.00
Construction of granular sub-base Cum 6900 1143 55.00 79.39 100.00
Wet mix macadam Cum 24370 4000   0.00 1000.00
Providing and laying 60 mm thick  interlocking paver block  sqm 210 22 15.00 0.00 5.00
Construction of embankment with red earth Cum 3890 214.2 50.00 0.00 100.00
Construction of embankment  of approved materials deposited at site  Cum 1050 214.49 12.50 0.00 12.50
plain concrete / reinforced concretefor sub-MORTH -M15 Cum 5070 1039.54 50.00 4.50 100.00
Cement concrete for plain concrete / reinforced concrete MORTH -M25 grade  Cum 510 105.706 5.00 56.64 5.00
 
Back
 
    
CUTTING NEAR BY TOSHIBA

    
    
CUTTING NEAR BY TOSHIBAJN

    
    
RETAINING WALL AT CH 9+040

    
    
RETAINING WALL WORK AT CH 9+400

    
 
    
PRIME COAT APPLIED OVER WMM

      
 

 

 

 

 

 

 

 