   10.12.2010
    
Progress Report For Mulankunnathukavu ROB for the week ending on 10-12-2010
Si No  Activity Description  Total Quantity Cumulative progress upto this week  Balance  work  Cumulative delay in weeks  Work  planned  during the week  Actual work done during the week  Delay for the week    Work  Planned for next week  Remarks 
1 PILE SHORNUR  SIDE 9 2 7 0 6 7 0 0  
2 PILE M.C SIDE 36 36 0 0 2 2 0 0  
3 PILE CAP SHORNUR SIDE 3 0 3 0 0 0 0 0  
4 PILE CAP  M.C SIDE 12 1 11 0 0 0 0 5  
5 PIER SHORNUR  SIDE 3 0 3 0 0 0 0 0  
6 PIER M.C SIDE 12 0 12 0 0 0 0 0  
7 PIER CAP SHORNUR  SIDE 3 0 3 0 0 0 0 0  
8 PIER CAP M.C SIDE 12 0 12 0 0 0 0 0  
9 RE/R WALL SHORNUR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
10 RE/R WALL M.C SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
11 BEAM/SLAB SHORNUR  SIDE 3 0 3 0 0 0 0 0  
12 BEAM/SLAB M.C SIDE 12 0 12 0 0 0 0 0  
13 HR/FP/KERB SHORNUR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
14 HR/FP/KERB M.C SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%   

 

 
Back
 
    
PILE CAP CONCRETING - 04.12.2010

    
    
PIER CONCRETING - 06.12.2010

    
    
PILE LOAD MATERIALS REMOVING - 07.12.2010

    
    
REINFORCEMENT WORK FOR PIER CAP - 08.12.2010

    
 
    
ERECTION OF REINFORCEMENT WORK FOR PILE - 09.12.2010

    
    
PIER CONCRETING - 10.12.2010

      
 

 

 

 

 

 

 

 