   Weekly Progress Report as on 21.02.2014
    
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 63 - - - - - -
2 Pile cap 21 21 - - - - - -
3 Pier  21 21 - - - - - -
4 PierCap 21 21 - - - - - -
5 Deck Slab 21 19 2 - - - - -
6 Hand Rails 21 19 2          
7 Expansion Joint 21 18 3   1 1 0 0
8 RC wall - Kuttipuram side 100% 100% 0% - 0% 0% 15% 0%
9 RC wall - Kanjipura side 100% 100% 0%   0% 0% 10% 0%
10 BOX culvert 100% 100% 0%   - - - -
11 CC wall kuttipuram side 100% 100% 0%             - 0% 0% 30% 0%
12 E/W  100% 95% 5%   10% 5% 100% 0%
13 Painting 100% 45% 55%   0% 0%   0%
14 RCC Drain NH Side 100% 90% 10%   10% 10%   0%
15 HR 100% 95% 5%   0% 0% 0% 0%
16 GSB Kanjippura 100% 25% 75%   5% 80% 70% 0%
17 WMM Kanjippura 100% 20% 80%     20% 30% 20%
18 Approach slab 100% 25% 0%   0% 75% 75% 0%
                   
Date 2/22/2014 2/24/2014 2/25/2014 2/26/2014 2/27/2014 2/28/2014      
No. of labours 1 1 1 1 1 1      
                   
                   
Availability of Materials                
                   
Material Required Available              
Fine aggregate 16 m3 24 m3              
Coarse Aggregate 32 m3  35 m3              
Cement 200 bags 200 bags              
Steel 5MT 7 MT              
 