PROGRESS OF ROB ALOOR-MALA WORK AS ON 21-02-2014. |
|
Description |
Completed/ Progress |
Remarks |
1 |
ROB ALOOR-MALA |
|
|
1 |
Piling |
Completed. |
completed 32/32 |
2 |
Pilecap |
In Progress |
COMPLETED 8OUT OF 8 |
3 |
Pier |
In Progress |
completed 8out of 8. |
4 |
Piercap |
In Progress |
6 nos completed out of 6. |
5 |
Girder |
started |
p1-p2 staging in progress.A1-P1 in progress. |
6 |
Slab |
Not started |
|
7 |
Handrail with kerb |
Not started |
|
8 |
Ex.joint |
Not started |
|
9 |
Tarring work |
Not started |
|
10 |
Service road work(Diversion road) |
In Progress |
aloor right side in progress 100% completed.Mala side LHS 100% |
11 |
Retaining wall work(Diversion road) |
started |
aloor right side in progress 62m WALL and 100 m raft COMPLETED, |
12 |
Load test . |
Completed. |
In P4 location. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|