Progress Report For Palakkad Sultanpet ROB for the week ending on10-12-2010 |
Si No |
Activity Description |
Total Quantity |
Cumulative progress upto this week |
Balance work |
Cumulative delay in weeks |
Work planned during the week |
Actual work done during the week |
Delay for the week |
Work Planned for next week |
Remarks |
1 |
PCC for RAFT PALAKKAD SIDE |
1 |
0 |
1 |
2 |
1 |
0 |
0 |
0 |
|
2 |
PCC for RAFT MOYAN SCHOOL SIDE |
3 |
1 |
2 |
0 |
1 |
1 |
0 |
1 |
|
4 |
RAFT PALAKKAD SIDE |
1 |
0 |
1 |
0 |
0 |
0 |
0 |
1 |
|
5 |
RAFT MOYAN SCHOOL SIDE |
3 |
0 |
3 |
0 |
0 |
0 |
0 |
0 |
|
7 |
PIER PALAKKAD SIDE |
1 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
|
8 |
PIER MOYAN SCHOOL SIDE |
3 |
0 |
3 |
0 |
0 |
0 |
0 |
0 |
|
10 |
PIER CAP PALAKKAD SIDE |
1 |
0 |
1 |
9 |
0 |
0 |
0 |
0 |
|
11 |
PIER CAP MOYAN SCHOOL SIDE |
3 |
0 |
3 |
8 |
0 |
0 |
0 |
0 |
|
13 |
RE/R WALL PALAKKAD SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
14 |
RE/R WALL MOYAN SCHOOL SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
16 |
BEAM/SLAB PALAKKAD SIDE |
2 |
0 |
2 |
0 |
0 |
0 |
0 |
0 |
|
17 |
BEAM/SLAB MOYAN SCHOOL SIDE |
4 |
0 |
4 |
0 |
0 |
0 |
1 |
0 |
|
18 |
BEAM/SLAB RAILWAY SPAN |
7 |
0 |
7 |
0 |
0 |
0 |
1 |
0 |
|
19 |
HR/FP/KERB CALICUT SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
20 |
HR/FP/KERB NH SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
21 |
HR/FP/KERB RAILWAY SPAN |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
22 |
BC/PAINTING |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|