   Weekly progress report as on 14.02.2014
    
Progress as on 14-02-14
  Description Completed/ Progress Remarks
  ROB Kainatty (P6-RP4)    
1 Levelling and consolidation of the ground for staging work completed  
2 Staging work completed  
3 Reinforcement bending work completed  
4 Bottom shuttering work for girder completed  
5 Reinforcement binding for girder completed  
6 Shuttering work for girder completed  
7 Concreting of girder completed  
8 Shuttering work for deck slab completed  
9 Reinforcement binding of deck slab completed  
10 Deck slab concrete completed  
11 MISCELLANEOUS WORK In progress  
11(a) Concreting of kerb, handrails completed  
11(b) Expansion joints completed  
12 ROAD WORK  Not started  
12(a) Aplplying mastic Asphault completed  
12(b) Applying bituminous concrete Not started  
13 PAINTING WORK In progress applying Paint
 
  Description Completed/ Progress Remarks
  ROB Kainatty (P5-RP1)    
1 Levelling and consolidation of the ground for staging work completed  
2 Staging work completed  
3 Reinforcement bending work completed  
4 Bottom shuttering work for girder completed  
5 Reinforcement binding for girder completed  
6 Shuttering work for girder completed  
7 Concreting of girder completed  
8 Shuttering work for deck slab completed  
9 Reinforcement binding of deck slab completed  
10 Deck slab concrete completed  
11 MISCELLANEOUS WORK In progress  
11(a) Concreting of kerb, handrails completed  
11(b) Expansion joints completed  
12 ROAD WORK Not started  
12(a) Aplplying mastic Asphault completed  
12(b) Applying bituminous concrete Not started  
13 PAINTING WORK In progress Applying prime coat
       
  Description Completed/ Progress Remarks
  STAIRCASE-NADAPURAM  EAST SIDE    
1 Earthwork in excavation completed  
2 P.C.C for foundation completed  
3  Concreting of foundations completed  
4 Concreting of columns completed  
5 Concreting of flights completed  
6 Brick work  completed  
7 Plastering work In progress In final stage
       
  Description Completed/ Progress Remarks
  STAIRCASE-NADAPURAM  WEST SIDE    
1 Earthwork in excavation completed  
2 P.C.C for foundation completed  
3  Concreting of foundations completed  
4 Concreting of columns completed  
5 Concreting of flights completed  
6 Brick work completed                                              
7 Plastering work Not Started  
       
  STAIRCASE-KAINATTY  EAST SIDE    
1 Earthwork in excavation completed  
2 P.C.C for foundation completed  
3  Concreting of foundations completed  
4 Concreting of columns completed  
5 Concreting of flights completed  
       
       
 