Prevoius Weekly Reports

   10.12.2010
    
 
Si No  Activity Description  Total Quantity Cumulative progress upto this week  Balance  work  Cumulative delay in weeks  Work  planned  during the week  Actual work done during the week  Delay for the week    Work  Planned for next week  Remarks 
1 PILE SHORNUR  SIDE 9 2 7 0 6 7 0 0  
2 PILE M.C SIDE 36 36 0 0 2 2 0 0  
3 PILE CAP SHORNUR SIDE 3 0 3 0 0 0 0 0  
4 PILE CAP  M.C SIDE 12 1 11 0 0 0 0 5  
5 PIER SHORNUR  SIDE 3 0 3 0 0 0 0 0  
6 PIER M.C SIDE 12 0 12 0 0 0 0 0  
7 PIER CAP SHORNUR  SIDE 3 0 3 0 0 0 0 0  
8 PIER CAP M.C SIDE 12 0 12 0 0 0 0 0  
9 RE/R WALL SHORNUR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
10 RE/R WALL M.C SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
11 BEAM/SLAB SHORNUR  SIDE 3 0 3 0 0 0 0 0  
12 BEAM/SLAB M.C SIDE 12 0 12 0 0 0 0 0  
13 HR/FP/KERB SHORNUR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
14 HR/FP/KERB M.C SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%   
 
Back
 
    
P 10 A CONCRETING - 04.12.2010

    
    
P 18 P C C - 07.12.2010

    
    
P 17 P C C - 07.12.2010

    
    
P 10 C CONCRETING -08.12.2010

    
 
    
P 9 B CONCRETING

    
    
P 6 C CONCRETING

      
 

 

 

 

 

 

 

 