   weekly progress as on 7.2.2014
    

 

Weekly Progress Report  Jan 2014  
Sl No Description Unit  Total Quantity Qty as on previous month Production for current month Upto date quantity
 Road Works      
  General Clearance          
1.01 Clearing and grubbing  Ha   2.02 0.00 2.02
1.02 Cutting of trees,  Nos   0.00 0.00 0.00
  a) Girth 300mm to 600 mm     14.00 0.00 14.00
  b) Girth 600mm to 900mm     11.00 0.00 11.00
  c) Girth 900mm to1800mm     4.00 0.00 4.00
  d) Girth above 1800 mm      0.00 0.00 0.00
1.03 Dismantlingof rubble masonry,   Cum   52.24 7.29 59.53
1.04 Dismantling ofblock/brick masonry  Cum   8.82 4.50 13.32
1.05 Dismantling of advertisement boards, sign boards   Nos   33.00 7.00 40.00
1.06 Dismantling of Reinforced cement concrete   Cum   2.99 0.00 2.99
1.07 Dismantling of  cement concrete Cum   11.27 1.50 12.77
1.08 Dismantling of flexible pavements  Cum   67.20 3.45 70.65
  Earthwork          
1.09 Excavation for roadway  Cum   1916.80 69.00 1985.80
1.10 Earthwork excavation including removal of unsuitable soil  Cum   6194.93 657.44 6852.37
  Road works-Pavement          
1.11 Loosening, levelingand Compacting original ground  Cum   289.31 126.60 415.90
1.12 Construction of sub grade  Cum   948.90 0.00 948.90
1.13 Construction of granular sub-base Cum   1606.89 107.09 1713.98
1.14 Wet mix macadam Cum   531.15 200.91 732.07
1.15 Primer coat Sqm   0.00 0.00 0.00
1.16 Tack coat Sqm   0.00 0.00 0.00
1.17 Bituminous macadam Cum   0.00 0.00 0.00
1.18 Dense graded bituminous macadam Cum   0.00 0.00 0.00
1.19 Bituminous concrete Cum   0.00 0.00 0.00
1.20 Providing kerb stone size 300x 300 x 150 mm Rm   0.00 0.00 0.00
1.21 Reinforced Cement Concrete Pipe NP4  Rm   0.00 0.00 0.00
1.22 Providing and laying 60 mm thick  interlocking paver block  sqm   0.00 0.00 0.00
1.23 Random Rubble Masonry  Cum   0.00 0.00 0.00
1.24 dry rubble masonry Cum   0.00 0.00 0.00
  Retaining wall and Drain     0.00    
1.25 Construction of embankment with approved material obtained from borrow pits  Cum   0.00 0.00 0.00
1.26 Construction of embankment with red earth   Cum   59.25 0.00 59.25
1.27 Construction of embankment  of approved materials deposited at site  Cum   9.20 49.00 58.20
1.28 plain concrete / reinforced concretefor sub-MORTH -M15 Cum   151.49 7.58 159.07
1.29 Cement concrete for plain concrete / reinforced concrete MORTH -M25 grade  Cum   675.35 87.13 762.48
1.30 Supplying, fitting and placing HYSD bar reinforcement in sub-structure  MT   29.17 2.35 31.52
1.31 Painting two coats  Sqm   0.00 0.00 0.00
  Signs, Markings and Markers     0.00    
1.32 Providing and laying of hot applied thermoplastic  Sqm   0.00 0.00 0.00
1.33 Supplying and installation of delineators Nos   0.00 0.00 0.00
1.34 Providing and fixing of road stud 100x 100 mm, Nos   0.00 0.00 0.00
1.35 Providing & fixing of red reflectors Nos   0.00 0.00 0.00
1.36 Providing and fixing M-20 grade concrete guard posts   Nos   57.00 0.00 57.00
1.37 Providing and fixing of retro- reflectorised sign      0.00 0.00 0.00
a Triangular 900 mm size Nos   0.00 0.00 0.00
b Circular 600 mm size Nos   0.00 0.00 0.00
c Informatory/Mandatory Signs 800mmx600mm Nos   0.00 0.00 0.00
d 900 mm high octagon Nos   0.00 0.00 0.00
1.38 Providing and erecting direction and place identification retro-reflectorised sign      0.00 0.00 0.00
a Object Hazard Marker for culverts,openings etc. sqm   0.00 0.00 0.00
b Chevron Signs 600mm x 600mm sqm   0.00 0.00 0.00
c Chevron Signs 1200mm x 600mm sqm   0.00 0.00 0.00
1.39 Providing and erecting direction and place identification retro- reflectorised sign      0.00 0.00 0.00
  a) Advanced Direction Sign Board (1800x1200 mm) sqm   0.00 0.00 0.00
1.40 Providing and erecting a "Thrie" metal beam crash barrier  Lm   0.00 0.00 0.00
1.41 Planting flowering plants and shrubs  KM   0.00 0.00 0.00
1.42 Maintenance of flowering plants and shrubs in central verge for 5 years  KM   0.00 0.00 0.00
1.43 Planting of trees by road sides Nos   0.00 0.00 0.00
 