![](file:///C:/DOCUME~1/ADMIN/LOCALS~1/Temp/msohtmlclip1/01/clip_image006.jpg)
Name of Work
|
:
|
STRENGTHENING, WIDENING AND EXTENSION OF TIPPU SULTHAN ROAD PHASE-1: CHAINAGE 0.000 TO 4.500 Km
|
Name of Client
|
:
|
RBDCK Ltd.
|
Name of Engineer
|
:
|
KITCO Ltd.
|
Name of Contractor
|
:
|
ULCCS Ltd.
|
Monthly Report No….4.... for the Month of JANUARY2014
Submitted by
|
Approved by
|
ANURAJ K.E.
SUB-ENGINEER
ULCCS Ltd.
|
ABDUL HAMEED E.K.
ENGINEER IN-CHARGE
KITCO Ltd.
|
![](file:///C:/DOCUME~1/ADMIN/LOCALS~1/Temp/msohtmlclip1/01/clip_image006.jpg)
CONTENTS
1. PROGRESS SUMMERY
2. AREAS OF CONCERN
3. OVERALL WORK PROGRESS
4. PERFORMANCE OF THIS MONTH LOOK AHEAD PROGRAMME
5. LOOK AHEAD PROGRAMME FOR NEXT MONTH
6. MANPOWER STATEMENT FOR THE MONTH
7. CONTRACTOR’S PLANT AND EQUIPMENT
8. QUALITY ASSURANCE AND CONTROL RECORDS
9. PROGRESS PHOTOGRAPHS
1.PROGRESS SUMMERY
Project Title
|
:
|
Strengthening, Widening And Extension Of Tippu Sulthan Road Phase-1: Chainage 0.00 To 4.50 Km
|
Contract No.
|
:
|
RBDC/TPS Road/T34/Vol. III/562
|
Client
|
:
|
RBDCK Ltd.
|
Engineer
|
:
|
KITCO Ltd.
|
Contractor
|
:
|
ULCCS Ltd.
|
Date Of Commencement
|
:
|
21-03-2013
|
Completion Period (Days)
|
:
|
365
|
Planned Completion Date
|
:
|
20-03-2014
|
Planned Contract Finish Date
|
:
|
20-03-2014
|
Forecasted Completion Date
|
:
|
20-03-2014
|
Elapsed Period (Days)
|
:
|
317
|
% Time Elapsed
|
:
|
86.85
|
Planned % Completion
|
:
|
32.94
|
Actual % Completion
|
:
|
29.44
|
Progress Variance
|
:
|
-3.50 %
|
Initial Contract Value
|
:
|
Rs. 177472377.00
|
Value Of Approved Variations
|
:
|
Nil
|
Up To Date Value Of Contract
|
:
|
Rs. 17,74,72,377.00
|
Value Of Work Completed
|
:
|
Rs. 4,12,89,365.60
|
% Value Of Completion
|
:
|
23.31
|
2.AREAS OF CONCERN
Sl No.
|
Area of Concern
|
Action Required
|
Responsibility
|
Expected Resolution by Date
|
Client
|
Engineer
|
Contractor
|
|
|
|
|
|
|
|
3. OVERALL WORK PROGRES (As per format attached)
4. PERFORMANCE OF THIS MONTH LOOK AHEAD PROGRAMM (As per format attached)
5. LOOK AHEAD PROGRAMME FOR NEXT MONTH (As per format attached)
6. MANPOWER STATEMENT FOR THE MONTH
SL.NO
|
DESIGNAITION
|
PRESENT
|
STAFF
|
PRESENT
|
Remarks
|
1
|
CARPENTER
|
-
|
PROJECT MANAGER
|
|
|
2
|
MASON
|
5
|
ASST. PROJECT MANAGER
|
|
|
3
|
STEEL FIXER
|
|
SITE ENGINEER
|
1
|
|
4
|
LABOUR
|
15
|
PLANT ENGINEER
|
|
|
|
|
5
|
STORE HELPER
|
|
QA/QC ENGINEER
|
1
|
|
6
|
ELECTRICIAN HELPER
|
|
QUANTITY SURVEYOR
|
|
|
|
|
|
7
|
SITE SECURITY
|
|
PLANNER
|
|
|
8
|
OFFICE BOY
|
|
SAFETY OFFICER
|
|
|
9
|
TEA BOY
|
|
SUPERVISORS
|
2
|
|
10
|
SWEEPER
|
|
FOREMAN
|
|
|
11
|
SAFETY ASST
|
|
JNR. FOREMAN
|
|
|
12
|
LAB. ASST
|
|
SURVEYOR
|
2
|
|
13
|
RECEPTIONIST
|
|
DRAUHTSMAN
|
|
|
14
|
DOCUMENT CONTROLLER
|
2
|
SECRETARY
|
|
|
15
|
TIME KEEPER
|
|
STORE KEEPER
|
|
|
16
|
OTHERS
|
15
|
OTHERS
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL
|
37
|
|
6
|
|
7. CONTRACTOR’S PLANT AND EQUIPMENT
SL.NO
|
MACHINERIES
|
OWN
|
HIRE
|
QTY
|
SL.NO
|
MACHINERIES
|
OWN
|
HIRE
|
QTY
|
1
|
Concrete Plant
|
1
|
-
|
1
|
10
|
JCB
|
-
|
2
|
2
|
2
|
Concrete Pumps
|
-
|
-
|
|
11
|
Excavator
|
1
|
1
|
2
|
3
|
Vibrator
|
1
|
-
|
1
|
12
|
Pick Up
|
-
|
-
|
-
|
4
|
Crane
|
-
|
1
|
1
|
13
|
Hot Mix Plant
|
-
|
-
|
-
|
5
|
Truck/Tipper
|
2
|
3
|
5
|
14
|
Paver Finisher
|
-
|
-
|
-
|
6
|
Tanker
|
1
|
-
|
1
|
15
|
Bitumen Finisher
|
-
|
-
|
-
|
7
|
Roller (Vibratory)
|
1
|
-
|
1
|
16
|
Pilling RIG
|
-
|
-
|
-
|
8
|
Roller (Static)
|
-
|
-
|
-
|
17
|
Lab Test Equipment
|
-
|
-
|
-
|
9
|
Generator
|
-
|
-
|
-
|
18
|
Others
|
1
|
-
|
1
|
8. QUALITY ASSURANCE AND CONTROL RECORDS
Sl No.
|
Item
|
Date submitted
|
Date Returned
|
Status
|
Remarks
|
1
|
NCR
|
|
|
|
|
2
|
Inspection requests
|
|
|
|
|
3
|
Calibration Certificates
|
|
|
|
|
4
|
Test Conducted
|
|
|
|
|
4a
|
Field Compaction
|
|
|
O.K
|
SUB-GRADE
|
4b
|
Field Compaction
|
|
|
O.K
|
GSB
|
4c
|
Gradation
|
|
|
O.K
|
GSB
|
4d
|
Field Compaction
|
|
|
O.K
|
WMM
|
4e
|
Gradation
|
|
|
O.K
|
WMM
|
Material
|
Up to date Qty delivered
|
Actual Consumption
|
Theoretical
Consumption
|
Remarks
|
Cement
|
3135 Bag
|
3130 Bag
|
3173 Bag
|
|
Steel
|
22.42 MT
|
21.48 MT
|
|
|
Red Earth
|
8000 m3
|
7207m3
|
|
|
GSB
|
8500 m3
|
6639 m3
|
|
|
WMM
|
6500 m3
|
5375 m3
|
|
|
Other
|
|
|
|
|
8.1Record of Control of Materials
9. PROGRESS PHOTOGRAPHS
|