Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7887471
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   weekly progress of 31-1-2014
    

                                                                                             

 

Name of Work

:

STRENGTHENING, WIDENING AND EXTENSION OF TIPPU SULTHAN ROAD PHASE-1: CHAINAGE 0.000 TO 4.500 Km

Name of Client

:

RBDCK Ltd.

Name of Engineer

:

KITCO Ltd.

Name of Contractor

:

ULCCS Ltd.

 

 

 

Monthly Report No….4.... for the Month of JANUARY2014

 

 

 

 

 

Submitted by

 

Approved by

 

 

 

ANURAJ K.E.

SUB-ENGINEER

ULCCS Ltd.

 

 

 

ABDUL HAMEED E.K.

ENGINEER IN-CHARGE

KITCO Ltd.

 

 

                                                                                                  

 

CONTENTS

1.    PROGRESS SUMMERY                              

2.   AREAS OF CONCERN

3.   OVERALL WORK PROGRESS

4.   PERFORMANCE OF THIS MONTH LOOK AHEAD PROGRAMME

5.   LOOK AHEAD PROGRAMME FOR NEXT MONTH

6.   MANPOWER STATEMENT FOR THE MONTH

7.   CONTRACTOR’S PLANT AND EQUIPMENT

8.   QUALITY ASSURANCE AND CONTROL RECORDS

9. PROGRESS PHOTOGRAPHS

 

 

 

 

 

 

1.PROGRESS SUMMERY                              

Project Title

:

Strengthening, Widening And Extension Of Tippu Sulthan Road Phase-1: Chainage 0.00 To 4.50 Km

Contract No.

:

RBDC/TPS Road/T34/Vol. III/562

Client

:

RBDCK Ltd.

Engineer

:

KITCO Ltd.

Contractor

:

ULCCS Ltd.

Date Of Commencement

:

21-03-2013

Completion Period (Days)

:

365

Planned  Completion Date

:

20-03-2014

Planned  Contract Finish Date

:

20-03-2014

Forecasted Completion  Date

:

20-03-2014

Elapsed Period (Days)

:

317

% Time Elapsed

:

86.85

Planned % Completion

:

32.94

Actual % Completion

:

29.44

Progress  Variance

:

-3.50 %

Initial Contract Value

:

Rs. 177472377.00

Value Of Approved Variations

:

Nil

Up To Date Value Of Contract

:

Rs. 17,74,72,377.00

Value Of Work Completed

:

Rs. 4,12,89,365.60

 

% Value Of Completion

:

23.31

 

 

2.AREAS OF CONCERN

Sl No.

Area of Concern

Action Required

Responsibility

Expected  Resolution by Date

Client

Engineer

Contractor

 

 

 

 

 

 

 

 

3.   OVERALL WORK  PROGRES (As per format attached)

4.   PERFORMANCE OF THIS MONTH LOOK AHEAD PROGRAMM (As per format attached)

5.   LOOK AHEAD PROGRAMME FOR NEXT MONTH (As per format attached)

6.   MANPOWER STATEMENT FOR THE MONTH

SL.NO

DESIGNAITION

PRESENT

STAFF

PRESENT

Remarks

1

CARPENTER

-

PROJECT MANAGER

 

 

2

MASON

5

ASST. PROJECT MANAGER

 

 

3

STEEL FIXER

 

SITE ENGINEER

1

 

4

LABOUR

15

PLANT ENGINEER

 

 

 

 

5

STORE HELPER

 

QA/QC ENGINEER

 1

 

6

ELECTRICIAN HELPER

 

QUANTITY SURVEYOR

 

 

 

 

 

7

SITE SECURITY

 

PLANNER

 

 

8

OFFICE BOY

 

SAFETY OFFICER

 

 

9

TEA BOY

 

SUPERVISORS

2

 

10

SWEEPER

 

FOREMAN

 

 

11

SAFETY ASST

 

JNR. FOREMAN

 

 

12

LAB. ASST

 

SURVEYOR

 

13

RECEPTIONIST

 

DRAUHTSMAN

 

 

14

DOCUMENT CONTROLLER

2

SECRETARY

 

 

15

TIME KEEPER

 

STORE KEEPER

 

 

16

OTHERS

15

OTHERS

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

37

 

6

 

 

7.   CONTRACTOR’S PLANT AND EQUIPMENT

SL.NO

MACHINERIES

OWN

HIRE

QTY

 SL.NO

MACHINERIES

OWN

HIRE

QTY

1

Concrete Plant

1

-

1

10

JCB

-

2

2

2

Concrete Pumps

-

-

 

11

Excavator

1

1

2

3

Vibrator

1

-

1

12

Pick Up

-

-

-

4

Crane

-

1

1

13

Hot Mix Plant

-

-

-

5

Truck/Tipper

2

3

5

14

Paver Finisher

-

-

-

6

Tanker

1

-

1

15

Bitumen Finisher

-

-

-

7

Roller (Vibratory)

1

-

1

16

Pilling RIG

-

-

-

8

Roller (Static)

-

-

-

17

Lab Test Equipment

-

-

-

9

Generator

-

-

-

18

Others

1

-

1

 

8.   QUALITY ASSURANCE AND CONTROL RECORDS

Sl No.

Item

Date submitted

Date Returned

Status

Remarks

1

NCR

 

 

 

 

2

Inspection requests

 

 

 

 

3

Calibration Certificates

 

 

 

 

4

Test Conducted

 

 

 

 

4a

Field Compaction

 

 

O.K

SUB-GRADE

4b

Field Compaction

 

 

O.K

GSB

4c

Gradation

 

 

O.K

GSB

4d

Field Compaction

 

 

O.K

WMM

4e

Gradation

 

 

O.K

WMM

 

Material

Up to date Qty delivered

Actual Consumption

Theoretical

Consumption

Remarks

Cement

3135 Bag

3130 Bag

3173 Bag

 

Steel

22.42 MT

21.48 MT

 

 

Red Earth

8000 m3

7207m3

 

 

GSB

8500 m3

6639 m3

 

 

WMM

6500 m3

5375 m3

 

 

Other

 

 

 

 

8.1Record of Control of Materials

9.           PROGRESS PHOTOGRAPHS

 
Back
 
    
WMM

    
    
WMM (4)

    
    
WMM (3)

    
    
WMM (2)

    
 
    
SUB GRADE FILLING

      
 

 

 

 

 

 

 

 

Untitled Document