   weekly progress as on 31.1.2014
    

 

UPGRADING OF EXISTING AIRPORT SEAPORT ROAD PHASE I TO 4 LANE FROM CHAINAGE 8.9 TO 11.3 KM  
Sl No Description Unit  Total Quantity Qty as on previous month Production for current month Upto date quantity
  General Clearance          
1.01 Clearing and grubbing  Ha   1.56 0.46 2.02
1.02 Cutting of trees, Nos   0.00 0.00 0.00
  a) Girth 300mm to 600 mm     0.00 14.00 14.00
  b) Girth 600mm to 900mm     0.00 11.00 11.00
  c) Girth 900mm to1800mm     0.00 4.00 4.00
  d) Girth above 1800 mm      0.00 0.00 0.00
1.03 Dismantlingof rubble masonry,   Cum   37.92 14.00 51.92
1.04 Dismantling ofblock/brick masonry  Cum   8.70 0.12 8.82
1.05 Dismantling of advertisement boards, sign boards   Nos     20.00 20.00
1.06 Dismantling of Reinforced cement concrete   Cum   0.96 2.03 2.99
1.07 Dismantling of  cement concrete Cum   5.13 6.14 11.27
1.08 Dismantling of flexible pavements  Cum   67.20 0.00 67.20
  Earthwork          
1.09 Excavation for roadway Cum   1864.80 52.00 1916.80
1.10 Earthwork excavation including removal of unsuitable soil  Cum   3554.57 2558.28 6112.85
  Road works-Pavement          
1.11 Loosening, levelingand Compacting original ground  Cum   216.93 72.38 289.31
1.12 Construction of sub grade  Cum   295.38 653.52 948.90
1.13 Construction of granular sub-base Cum   528.00 1038.39 1566.39
1.14 Wet mix macadam Cum   30.00 501.15 531.15
1.26 Construction of embankment with red earth Cum   59.25 0.00 59.25
1.27 Construction of embankment  of approved materials deposited at site  Cum   0.00 9.20 9.20
1.28 plain concrete / reinforced concretefor sub-MORTH -M15 Cum   106.20 45.29 151.49
1.29 Cement concrete for plain concrete / reinforced concrete MORTH -M25 grade  Cum   270.79 388.25 659.04
1.30 Supplying, fitting and placing HYSD bar reinforcement in sub-structure  MT   23.42 5.15 28.57
1.36 Providing and fixing M-20 grade concrete guard posts   Nos   27.00 30.00 57.00
 