Road to Prosperity
Site last updated on: 12-12-2020 | You are visitor:
7888120
Contact Us
Login
Home
About Us
Vision
Profile
Board of Directors
Organization Chart
Staff Profile
Articles Of Association
Projects
At a Glance
Completed Projects
Projects Under Construction
Tendering stage
Land Acquisition in Progress
DPR under KIIFB review
DPR under preparation
Toll Collection
KIIFB Projects
Acts & Rules
Right to Information
Tenders
Corporate Governance
Annual Accounts
Annual Reports
Photo Gallery
Completed Projects
Projects Under Construction
Citizen Services
Careers
Right to Service
Prevoius Weekly Reports
Weekly progress report as on 24.01.2014
PROGRESS OF ROB ALOOR-MALA WORK AS ON 24-1-2014.
Description
Completed/ Progress
Remarks
1
ROB ALOOR-MALA
1
Piling
Completed.
completed 32/32
2
Pilecap
In Progress
COMPLETED 8OUT OF 8
3
Pier
In Progress
completed 7out of 8.
4
Piercap
In Progress
3 nos completed out of 6.
5
Girder
started
p1-p2 staging in progress.
6
Slab
Not started
7
Handrail with kerb
Not started
8
Ex.joint
Not started
9
Tarring work
Not started
10
Service road work
In Progress
aloor right side in progress 100% completed.Mala side LHS 100%
11
Retaining wall work
started
aloor right side in progress 40m RAFT and 15 m wall COMPLETED .
12
Load test .
Completed.
In P4 location.