Name of Work : STRENGTHENING, WIDENING & EXTENSION OF
TIPPU SULTAN ROAD- PHASE-1 CH. 0.00 to 4.50 Km
Name of Client : RBDCK Ltd.
Name of Engineer : KITCO Ltd.
Name of Contractor : ULCCS Ltd.
Weekly Report No. 13 for the Week ending on 17-01-2014
Submitted by
|
Approved by
|
ANURAJ K.E.
SUB-ENGINEER
ULCCS Ltd.
|
ABDUL HAMEED E.K.
ENGINEER IN-CHARGE
KITCO Ltd.
|
CONTENTS
1. PROGRESS SUMMERY
2. AREAS OF CONCERNS
3. OVERALL WORK PROGRESS
4. PERFORMANCE OF THIS WEEK PROGRAMME
5. PROGRAMME FOR NEXT WEEK
6. MANPOWER STATEMENT FOR THE WEEK
7. CONTRACTOR’S PLANT AND EQUIPEMNT SCHEDULE
8. QUALITY ASSURANCE / QUALITY CONTROL RECORDS
9. PROGRESS PHOTOGRAPHS
1. PROGRESS SUMMERY
Project Title
|
:
|
STRENGTHENING, WIDENING & EXTENSION OF TIPPU SULTHAN ROAD PHASE 1 – CH 0.000 TO 4.500 Km
|
Contract No.
|
:
|
RBDC/TPS Road/T34/Vol. III/562
|
Client
|
:
|
RBDCK Ltd.
|
Engineer
|
:
|
KITCO Ltd.
|
Contractor
|
:
|
ULCCS Ltd.
|
Date of Commencement
|
:
|
21-03-2013
|
Completion Period (Days)
|
:
|
365
|
Planned Completion Date
|
:
|
20-03-2014
|
Planned Contract Finish Date
|
:
|
20-03-2014
|
Forecasted Completion Date
|
:
|
20-03-2019
|
Elapsed Period (Days)
|
:
|
303
|
% Time Elapsed
|
:
|
83.01
|
% Appr. Physical Completion
|
:
|
48.50
|
% Appr. Financial Completion
|
:
|
21.23
|
2. AREAS OF CONCERNS
Sl No.
|
Area of Concern
|
Action Required
|
Responsibility
|
Expected Resolution by Date
|
Client
|
Engineer
|
Contractor
|
1
|
BM,DBM works
|
Mobilisation of Equipments.
|
|
|
ULCCS Ltd.
|
27 JAN 2014
|
2
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3. OVERALL WORK PROGRESS
Sl No
|
Item / Work
|
Unit
|
Previous Cumulative progress
|
This Week Progress
|
Cumulative Progress up to 10-01-14
|
|
|
1
|
Earthwork Excavation Roadway
|
m3
|
17881
|
80
|
17961
|
|
2
|
Loosening & Leveling
|
m3
|
3373
|
15
|
3388
|
|
3
|
Sub-grade
|
m3
|
6632
|
65
|
6697
|
|
4
|
GSB
|
m3
|
6179
|
55
|
6234
|
|
5
|
WMM
|
m3
|
3745
|
475
|
4220
|
|
6
|
Dismantling RRM
|
m3
|
163
|
--
|
163
|
|
7
|
Dismantling CC
|
m3
|
125.694
|
--
|
125.694
|
|
8
|
Earthwork Excavation Culvert
|
m3
|
1196
|
--
|
1196
|
|
9
|
PCC M15
|
m3
|
53.6
|
--
|
53.6
|
|
10
|
Wing Wall M35
|
m3
|
41.4
|
--
|
41.4
|
|
11
|
HYSD Bar
|
kg
|
18171
|
--
|
18171
|
|
12
|
Site Clearance
|
ha
|
2.09
|
0.04
|
2.13
|
|
13
|
DRM
|
m3
|
33
|
--
|
33
|
|
14
|
RRM
|
m3
|
556
|
--
|
556
|
|
4. PERFORMANCE OF THIS WEEK PROGRAMME
Sl. No
|
Item / Work
|
Location
|
Unit
|
Planned Quantity
|
Executed quantity
|
|
|
1
|
Earthwork Excavation Roadway
|
2/900 - 3/100 LHS
|
m3
|
750
|
80
|
|
2
|
Loosening & Leveling
|
2/900 - 3/100 LHS
|
m3
|
100
|
15
|
|
3
|
Sub-grade
|
2/900 - 3/100 LHS
|
m3
|
300
|
65
|
|
4
|
GSB
|
2/900 - 3/100 LHS
|
m3
|
250
|
55
|
|
5
|
WMM
|
2/900 - 3/100 LHS &
2/750 – 2/390 RHS
|
m3
|
500
|
475
|
|
6
|
Earthwork Excavation Culvert
|
|
m3
|
--
|
--
|
|
7
|
PCC M15
|
|
m3
|
--
|
--
|
|
8
|
Wing Wall M35
|
|
m3
|
--
|
--
|
|
9
|
HYSD Bar
|
|
kg
|
--
|
--
|
|
10
|
Site Clearance
|
2/900 - 3/100 LHS
|
ha
|
0.15
|
0.04
|
|
11
|
DRM
|
|
m3
|
--
|
--
|
|
12
|
RRM
|
|
m3
|
--
|
--
|
|
5. PROGRAMME FOR NEXT WEEK
Sl No
|
Item / Work
|
Unit
|
Planned Quantity Next week
|
|
|
1
|
Earthwork Excavation
|
m3
|
550
|
|
2
|
Loosening & Leveling
|
m3
|
50
|
|
3
|
Sub-grade
|
m3
|
200
|
|
4
|
GSB
|
m3
|
200
|
|
5
|
WMM
|
m3
|
500
|
|
6
|
Earthwork Excavation Culvert
|
m3
|
--
|
|
7
|
PCC M15
|
m3
|
--
|
|
8
|
Wing Wall M35
|
m3
|
--
|
|
9
|
HYSD Bar
|
kg
|
--
|
|
10
|
Site Clearance
|
ha
|
0.10
|
|
11
|
DRM
|
m3
|
--
|
|
12
|
RRM
|
m3
|
--
|
|
6. MANPOWER STATEMENT FOR THE WEEK
SL.NO
|
DESIGNAITION
|
PRESENT
|
STAFF
|
PRESENT
|
Remarks
|
1
|
Carpenter
|
-
|
Project Manager
|
|
|
2
|
Mason
|
5
|
Asst. Project Manager
|
|
|
3
|
Steel Fixer
|
|
Site Engineer
|
1
|
|
4
|
Labour
|
15
|
Plant Engineer
|
|
|
5
|
Store Helper
|
|
QA/QC Engineer
|
1
|
|
6
|
Electrician Helper
|
|
Quantity Surveyor
|
|
|
7
|
Site Security
|
|
Planner
|
|
|
8
|
Office Boy
|
|
Safety Officer
|
|
|
9
|
Tea Boy
|
|
Supervisors
|
2
|
|
10
|
Sweeper
|
|
Foreman
|
|
|
11
|
Safety Asst
|
|
Jnr. Foreman
|
|
|
12
|
Lab. Asst
|
|
Surveyor
|
2
|
|
13
|
Receptionist
|
|
Draughtsman
|
|
|
14
|
Document Controller
|
2
|
Secretary
|
|
|
15
|
Time Keeper
|
|
Store Keeper
|
|
|
16
|
Others
|
15
|
Others
|
|
|
|
TOTAL
|
37
|
|
6
|
|
7. CONTRACTOR’S PLANT AND EQUIPEMNT SCHEDULE
SL.NO
|
MACHINERIES
|
OWN
|
HIRE
|
QTY
|
SL.NO
|
MACHINERIES
|
OWN
|
HIRE
|
QTY
|
1
|
Concrete Plant
|
1
|
-
|
1
|
10
|
JCB
|
-
|
2
|
2
|
2
|
Concrete Pumps
|
-
|
-
|
|
11
|
Excavator
|
1
|
1
|
2
|
3
|
Vibrator
|
1
|
-
|
1
|
12
|
Pick Up
|
-
|
-
|
-
|
4
|
Crane
|
-
|
-
|
-
|
13
|
Hot Mix Plant
|
-
|
-
|
-
|
5
|
Truck/Tipper
|
2
|
3
|
5
|
14
|
Paver Finisher
|
-
|
-
|
-
|
6
|
Tanker
|
1
|
-
|
1
|
15
|
Bitumen Finisher
|
-
|
-
|
-
|
7
|
Roller (Vibratory)
|
1
|
1
|
2
|
16
|
Pilling RIG
|
-
|
-
|
-
|
8
|
Roller (Static)
|
-
|
-
|
-
|
17
|
Lab Test Equipment
|
-
|
-
|
-
|
9
|
Generator
|
-
|
-
|
-
|
18
|
Others
|
1
|
-
|
1
|
8. QUALITY ASSURANCE / QUALITY CONTROL RECORDS
Sl No.
|
Item
|
Date submitted
|
Date Returned
|
Status
|
Remarks
|
1
|
NCR
|
-
|
-
|
-
|
-
|
2
|
Inspection requests
|
|
|
|
18 No.s
|
3
|
Calibration Certificates
|
|
|
|
|
4
|
Test Conducted
|
|
|
|
|
4a
|
FIELD COMPACTION
|
|
|
O.K
|
SUB-GRADE ( 1 tests)
|
4b
|
FIELD COMPACTION
|
|
|
O.K
|
GSB(1 tests)
|
4c
|
FIELD COMPACTION
|
|
|
O.K
|
WMM(5 tests)
|
4d
|
GRADATION
|
|
|
O.K
|
GSB(1 tests)
|
4e
|
GRADATION
|
|
|
O.K
|
WMM(5 tests)
|
Any Other Quality Related Issues
|
|
|
9. PROGRESS PHOTOGRAPHS(Attached)
|