   weekly progress of 29-11-2013
    

                                                                               

 

Name of Work               : STRENGTHENING, WIDENING & EXTENSION OF

                                        TIPPU SULTAN ROAD- PHASE-1 CH. 0.00 to 4.50 Km

Name of Client             : RBDCK Ltd.

Name of Engineer         : KITCO Ltd.

Name of Contractor     : ULCCS Ltd.

 

 

 

Weekly Report No.    for the Week ending  29-11-2013

 

 

 

 

 

Submitted by

 

Approved by

 

 

 

 

ANURAJ K.E.

SUB-ENGINEER

ULCCS Ltd.

 

 

 

 

ABDUL HAMEED E.K.

ENGINEER IN-CHARGE

KITCO Ltd.

 

 

CONTENTS

1.    PROGRESS SUMMERY                              

2.    AREAS OF CONCERNS

3.    OVERALL WORK  PROGRESS

4.    PERFORMANCE OF THIS WEEK PROGRAMME

5.    PROGRAMME FOR NEXT WEEK

6.    MANPOWER STATEMENT FOR THE WEEK

7.    CONTRACTOR’S PLANT AND EQUIPEMNT SCHEDULE

8.    QUALITY ASSURANCE / QUALITY CONTROL RECORDS

9.    PROGRESS PHOTOGRAPHS

 

 

 

 

 

 

 

 

 

 

 

 

 

1.   PROGRESS SUMMERY                              

Project Title

:

STRENGTHENING, WIDENING & EXTENSION OF TIPPU SULTHAN ROAD PHASE 1 – CH 0.000 TO 4.500 Km

Contract No.

:

RBDC/TPS Road/T34/Vol. III/562

Client

:

RBDCK Ltd.

Engineer

:

KITCO Ltd.

Contractor

:

ULCCS Ltd.

Date of Commencement

:

21-03-2013

Completion Period (Days)

:

365

Planned  Completion Date

:

20-03-2014

Planned  Contract Finish Date

:

20-03-2014

Forecasted Completion  Date

:

20-03-2019

Elapsed Period (Days)

:

254

% Time Elapsed

:

69.58

% Appr. Physical Completion

:

40

% Appr. Financial Completion

:

14.3

 

2.   AREAS OF CONCERNS

Sl No.

Area of Concern

Action Required

Responsibility

Expected  Resolution by Date

Client

Engineer

Contractor

1

UTILITY SHIFTING

SHIFTING OF ELECTRIC POST AND TRANSFORMER

RBDCK

--

KSEB VETTOM DIVISION

03-12-13

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

3.   OVERALL WORK  PROGRESS

Sl No

Item / Work

Unit

Previous Cumulative progress

This Week Progress

Cumulative Progress up to 29-11-13

 
 

1

Earthwork Excavation

m3

12106

1510

13616

 

2

Loosening & Leveling

m3

2183

340

2523

 

3

Sub-grade

m3

4132

590

4722

 

4

GSB

m3

3859

560

4419

 

5

WMM

m3

968

200

1168

 

6

Dismantling RRM

 

78

85

163

 

7

Dismantling CC

m3

125.69

-

125.69

 

8

Earthwork Excavation Culvert

m3

1196

-

1196

 

9

PCC M15

m3

53.6

-

53.6

 

10

Wing Wall M35

m3

41.4

-

41.4

 

11

HYSD Bar

kg

18171

-

18171

 

12

Site Clearance

ha

1.24

0.2

1.44

 

13

DRM

m3

33

-

33

 

14

RRM

m3

556

-

556

 

 

 

 

 

 

 

 

 

 

 

4.   PERFORMANCE OF THIS WEEK PROGRAMME

Sl. No

Item / Work

Location

Unit

Planned Quantity

Executed quantity

 
 

1

Earthwork Excavation

0/280 - 0/000 RHS

m3

1650

1510

 

2

Loosening & Leveling

0/280 - 0/000 RHS

m3

350

340

 

3

Sub-grade

0/430 - 0/000 RHS

m3

560

590

 

4

GSB

0/430 - 0/000 RHS

m3

520

560

 

5

WMM

0/440-0/340 RHS

m3

250

200

 
 

Dismantling RRM

 

m3

85

85

 

6

Earthwork Excavation Culvert

 

m3

10

-

 

7

PCC M15

 

m3

-

-

 

8

Wing Wall M35

 

m3

4

-

 

9

HYSD Bar

 

kg

400

-

 

10

Site Clearance

 

ha

0.3

0.2

 

11

DRM

 

m3

15

-

 

12

RRM

 

m3

5

-

 
 

 

5.   PROGRAMME FOR NEXT WEEK

Sl No

Item / Work

Unit

Planned Quantity Next week

 
 

1

Earthwork Excavation

m3

1550

 

2

Loosening & Leveling

m3

320

 

3

Sub-grade

m3

520

 

4

GSB

m3

500

 

5

WMM

m3

550

 

6

Earthwork Excavation Culvert

m3

--

 

7

PCC M15

m3

--

 

8

Wing Wall M35

m3

--

 

9

HYSD Bar

kg

--

 

10

Site Clearance

ha

0.25

 

11

DRM

m3

--

 

12

RRM

m3

--

 
 

6.   MANPOWER STATEMENT FOR THE WEEK

SL.NO

DESIGNAITION

PRESENT

STAFF

PRESENT

Remarks

1

Carpenter

-

Project Manager

 

 

2

Mason

5

Asst. Project Manager

 

 

3

Steel Fixer

 

Site Engineer

1

 

4

Labour

15

Plant Engineer

 

 

5

Store Helper

 

QA/QC Engineer

 1

 

6

Electrician Helper

 

Quantity Surveyor

 

 

7

Site Security

 

Planner

 

 

8

Office Boy

 

Safety Officer

 

 

9

Tea Boy

 

Supervisors

2

 

10

Sweeper

 

Foreman

 

 

11

Safety Asst

 

Jnr. Foreman

 

 

12

Lab. Asst

 

Surveyor

 

13

Receptionist

 

Draughtsman

 

 

14

Document Controller

2

Secretary

 

 

15

Time Keeper

 

Store Keeper

 

 

16

Others

15

Others

 

 

 

TOTAL

37

 

6

 

 

7.   CONTRACTOR’S PLANT AND EQUIPEMNT SCHEDULE

SL.NO

MACHINERIES

OWN

HIRE

QTY

 SL.NO

MACHINERIES

OWN

HIRE

QTY

1

Concrete Plant

1

-

1

10

JCB

-

2

2

2

Concrete Pumps

-

-

 

11

Excavator

1

1

2

3

Vibrator

1

-

1

12

Pick Up

-

-

-

4

Crane

-

-

-

13

Hot Mix Plant

-

-

-

5

Truck/Tipper

2

3

5

14

Paver Finisher

-

-

-

6

Tanker

1

-

1

15

Bitumen Finisher

-

-

-

7

Roller (Vibratory)

1

1

2

16

Pilling RIG

-

-

-

8

Roller (Static)

-

-

-

17

Lab Test Equipment

-

-

-

9

Generator

-

-

-

18

Others

1

-

1

 

 

8.   QUALITY ASSURANCE / QUALITY CONTROL RECORDS

Sl No.

Item

Date submitted

Date Returned

Status

Remarks

1

NCR

-

-

-

-

2

Inspection requests

 

 

 

16

3

Calibration Certificates

 

 

 

 

4

Test Conducted

 

 

 

 

4a

FIELD COMPACTION

 

 

O.K

SUB-GRADE         ( 3 tests)

4b

FIELD COMPACTION

 

 

O.K

GSB ( 3 tests)

4c

GRADATION

 

 

O.K

GSB (3 tests)

4d

GRADATION

 

 

O.K

WMM(1test)

Any Other Quality Related Issues

 

 

 

9.   PROGRESS PHOTOGRAPHS(Attached)

 