Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7888269
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   weekly progress of 19-11-2013
    
                                                                                

 

Name of Work               : STRENGTHENING, WIDENING & EXTENSION OF

                                        TIPPU SULTAN ROAD- PHASE-1 CH. 0.00 to 4.50 Km

Name of Client             : RBDCK Ltd.

Name of Engineer         : KITCO Ltd.

Name of Contractor     : ULCCS Ltd.

 

 

 

Weekly Report No.    for the Week ending on 22-11-2013

 

 

 

 

 

Submitted by

 

Approved by

 

 

 

 

ANURAJ K.E.

SUB-ENGINEER

ULCCS Ltd.

 

 

 

 

ABDUL HAMEED E.K.

ENGINEER IN-CHARGE

KITCO Ltd.

 

 

CONTENTS

1.    PROGRESS SUMMERY                              

2.    AREAS OF CONCERNS

3.    OVERALL WORK  PROGRESS

4.    PERFORMANCE OF THIS WEEK PROGRAMME

5.    PROGRAMME FOR NEXT WEEK

6.    MANPOWER STATEMENT FOR THE WEEK

7.    CONTRACTOR’S PLANT AND EQUIPEMNT SCHEDULE

8.    QUALITY ASSURANCE / QUALITY CONTROL RECORDS

9.    PROGRESS PHOTOGRAPHS

 

 

 

 

 

 

 

 

 

 

 

 

 

1.   PROGRESS SUMMERY                              

Project Title

:

STRENGTHENING, WIDENING & EXTENSION OF TIPPU SULTHAN ROAD PHASE 1 – CH 0.000 TO 4.500 Km

Contract No.

:

RBDC/TPS Road/T34/Vol. III/562

Client

:

RBDCK Ltd.

Engineer

:

KITCO Ltd.

Contractor

:

ULCCS Ltd.

Date of Commencement

:

21-03-2013

Completion Period (Days)

:

365

Planned  Completion Date

:

20-03-2014

Planned  Contract Finish Date

:

20-03-2014

Forecasted Completion  Date

:

20-03-2019

Elapsed Period (Days)

:

247

% Time Elapsed

:

67.67

 

2.   AREAS OF CONCERNS

Sl No.

Area of Concern

Action Required

Responsibility

Expected  Resolution by Date

Client

Engineer

Contractor

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

3.   OVERALL WORK  PROGRESS

Sl No

Item / Work

Unit

Previous Cumulative progress

This Week Progress

Cumulative Progress up to 22-11-13

 
 

1

Earthwork Excavation

m3

10456

1650

12106

 

2

Loosening & Leveling

m3

1858

325

2183

 

3

Sub-grade

m3

3607

525

4132

 

4

GSB

m3

3369

490

3859

 

5

WMM

m3

968

-

968

 

6

Dismantling CC

m3

125.69

-

125.69

 

7

Earthwork Excavation Culvert

m3

1186

10

1196

 

8

PCC M15

m3

53.6

-

53.6

 

9

Wing Wall M35

m3

37.4

4

41.4

 

10

HYSD Bar

kg

17741

430

18171

 

11

Site Clearance

ha

0.94

0.3

1.24

 

12

DRM

m3

28

5

33

 

13

RRM

m3

552

4

556

 

14

GUARD STONE

No.s

-

-

506

 

 

 

 

 

 

 

 

 

 

 

4.   PERFORMANCE OF THIS WEEK PROGRAMME

Sl. No

Item / Work

Location

Unit

Planned Quantity

Executed quantity

 
 

1

Earthwork Excavation

0/280 - 0/600 RHS

M3

1600

1650

 

2

Loosening & Leveling

0/280 - 0/600 RHS

M3

320

325

 

3

Sub-grade

0/430 - 0/720 RHS

M3

520

525

 

4

GSB

0/430 - 0/720 RHS

M3

480

490

 

5

WMM

 

M3

250

-

 

6

Earthwork Excavation Culvert

 

M3

10

10

 

7

PCC M15

 

M3

-

-

 

8

Wing Wall M35

 

M3

4

4

 

9

HYSD Bar

 

kg

400

430

 

10

Site Clearance

 

ha

0.3

0.3

 

11

DRM

 

M3

15

5

 

12

RRM

 

M3

5

4

 
 

 

5.   PROGRAMME FOR NEXT WEEK

Sl No

Item / Work

Unit

Planned Quantity

 
 

1

Earthwork Excavation

m3

1650

 

2

Loosening & Leveling

m3

350

 

3

Sub-grade

m3

560

 

4

GSB

m3

520

 

5

WMM

m3

250

 

6

Earthwork Excavation Culvert

m3

10

 

7

PCC M15

m3

-

 

8

Wing Wall M35

m3

4

 

9

HYSD Bar

kg

400

 

10

Site Clearance

ha

0.3

 

11

DRM

m3

15

 

12

RRM

m3

5

 
 

 

 

 

6.   MANPOWER STATEMENT FOR THE WEEK

SL.NO

DESIGNAITION

PRESENT

STAFF

PRESENT

Remarks

1

Carpenter

-

Project Manager

 

 

2

Mason

5

Asst. Project Manager

 

 

3

Steel Fixer

 

Site Engineer

1

 

4

Labour

15

Plant Engineer

 

 

5

Store Helper

 

QA/QC Engineer

 1

 

6

Electrician Helper

 

Quantity Surveyor

 

 

7

Site Security

 

Planner

 

 

8

Office Boy

 

Safety Officer

 

 

9

Tea Boy

 

Supervisors

2

 

10

Sweeper

 

Foreman

 

 

11

Safety Asst

 

Jnr. Foreman

 

 

12

Lab. Asst

 

Surveyor

 

13

Receptionist

 

Draughtsman

 

 

14

Document Controller

2

Secretary

 

 

15

Time Keeper

 

Store Keeper

 

 

16

Others

15

Others

 

 

 

TOTAL

37

 

6

 

 

7.   CONTRACTOR’S PLANT AND EQUIPEMNT SCHEDULE

SL.NO

MACHINERIES

OWN

HIRE

QTY

 SL.NO

MACHINERIES

OWN

HIRE

QTY

1

Concrete Plant

1

-

1

10

JCB

-

2

2

2

Plate Rammer

1

-

1

11

Excavator

1

1

2

3

Vibrator

1

-

1

12

Pick Up

-

-

-

4

Crane

-

-

-

13

Hot Mix Plant

-

-

-

5

Truck/Tipper

2

3

5

14

Paver Finisher

-

-

-

6

Tanker

1

-

1

15

Bitumen Finisher

-

-

-

7

Roller (Vibratory)

-

1

1

16

Pilling RIG

-

-

-

8

Roller (Static)

-

-

-

17

Lab Test Equipment

-

-

-

9

Generator

-

-

-

18

Others

1

-

1

 

8.   QUALITY ASSURANCE / QUALITY CONTROL RECORDS

Sl No.

Item

Date submitted

Date Returned

Status

Remarks

1

NCR

-

-

-

-

2

Inspection requests

-

-

-

16 No.s

3

Calibration Certificates

-

-

-

-

4

Test Conducted

 

 

 

 

4a

FIELD COMPACTION

 

 

O.K

SUB-GRADE         ( 4 tests)

4b

FIELD COMPACTION

 

 

O.K

GSB( 4 tests)

4c

GRADATION

 

 

O.K

GSB(2  tests)

Any Other Quality Related Issues

 

 

 

9.   PROGRESS PHOTOGRAPHS(Attached)

 
Back
 
    
WING WALL CH637(RHS)

    
    
SUB GRADE CH950-800(RHS)

    
    
GSB800-950(RHS)

    
    
GSB CH1100-1200(RHS)

    
 
    
GSB 950-850(RHS)

    
    
EXCAVATION CH800-850(RHS)

    
    
CH850-900(RHS)

    
 
    
CH 800-950(RHS)

    
    
4. CH. 0.550 TO 0.600 KM (RHS)-GSB

    
    
3. CH. 0440 TO 0.530 KM (RHS)-SUBGRADE

    
 
    
2. CH. 0.620 TO 0.520 KM (RHS)-SUBGRADE

    
    
1. CH 0.300 TO 0.400 KM (RHS)-EXCAVATION

      
 

 

 

 

 

 

 

 

Untitled Document