   weekly progress of 5-11-2013
    

                                                                               

 

 

Name of Work               : STRENGTHENING, WIDENING & EXTENSION OF

                                        TIPPU SULTAN ROAD- PHASE-1 CH. 0.00 to 4.50 Km

Name of Client             : RBDCK Ltd.

Name of Engineer         : KITCO Ltd.

Name of Contractor     : ULCCS Ltd.

 

 

 

Weekly Report No.    for the Week ending  02-11-2013

 

 

 

 

 

Submitted by

 

Approved by

 

 

 

 

ANURAJ K.E.

SUB-ENGINEER

ULCCS Ltd.

 

 

 

 

ABDUL HAMEED E.K.

ENGINEER IN-CHARGE

KITCO Ltd.

 

 

 

CONTENTS

1.    PROGRESS SUMMERY                              

2.    AREAS OF CONCERNS

3.    OVERALL WORK  PROGRESS

4.    PERFORMANCE OF THIS WEEK PROGRAMME

5.    PROGRAMME FOR NEXT WEEK

6.    MANPOWER STATEMENT FOR THE WEEK

7.    CONTRACTOR’S PLANT AND EQUIPEMNT SCHEDULE

8.    QUALITY ASSURANCE / QUALITY CONTROL RECORDS

9.    PROGRESS PHOTOGRAPHS

 

 

 

 

 

 

 

 

 

 

 

 

 

1.   PROGRESS SUMMERY                              

Project Title

:

STRENGTHENING, WIDENING & EXTENSION OF TIPPU SULTHAN ROAD PHASE 1 – CH 0.000 TO 4.500 Km

Contract No.

:

 

Client

:

RBDCK Ltd.

Engineer

:

KITCO Ltd.

Contractor

:

ULCCS Ltd.

Date of Commencement

:

21-03-2013

Completion Period (Days)

:

365

Planned  Completion Date

:

20-03-2014

Planned  Contract Finish Date

:

20-03-2019

Forecasted Completion  Date

:

20-03-2014

Elapsed Period (Days)

:

226

% Time Elapsed

:

61.92

 

2.   AREAS OF CONCERNS

Sl No.

Area of Concern

Action Required

Responsibility

Expected  Resolution by Date

Client

Engineer

Contractor

1

TREE CUTTING

COMPLETION

 

 

Mr. M.K. ABOOBACKER

05-10-2013

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

3.   OVERALL WORK  PROGRESS

Sl No

Item / Work

Unit

Previous Cumulative progress

This Week Progress

Cumulative Progress up to 1-11-13

 
 

1

Earthwork Excavation

m3

5511

1650

7161

 

2

Loosening & Leveling

m3

953

290

1243

 

3

Sub-grade

m3

1907

630

2537

 

4

GSB

m3

1784

600

2384

 

5

WMM

m3

158

180

338

 

6

Dismantling CC

m3

57.694

-

57.694

 

7

Earthwork Excavation Culvert

m3

1090

30

1120

 

8

PCC M15

m3

50.5

1.1

51.6

 

9

Wing Wall M35

m3

22

2.5

24.5

 

10

HYSD Bar

kg

15836

220

16056

 

11

Site Clearance

ha

0.5

0.04

0.54

 

12

DRM

m3

-

4

4

 

13

RRM

m3

493

10

503

 

 

 

 

 

 

 

 

 

 

 

4.   PERFORMANCE OF THIS WEEK PROGRAMME

Sl. No

Item / Work

Location

Unit

Planned Quantity

Executed quantity

 
 

1

Earthwork Excavation

1/480 - 2/140 RHS

m3

1700

1650

 

2

Loosening & Leveling

1/480 - 2/140 RHS

m3

300

290

 

3

Sub-grade

1/550 - 2/270 RHS

m3

600

630

 

4

GSB

1/550 - 2/270 RHS

m3

550

600

 

5

WMM

3/180 - 3/450

m3

250

180

 

6

Earthwork Excavation Culvert

 

m3

75

30

 

7

PCC M15

 

m3

5

1.1

 

8

Wing Wall M35

 

m3

5

2.5

 

9

HYSD Bar

3/481

kg

400

220

 

10

Site Clearance

 

ha

0.1

0.04

 

11

DRM

 

m3

15

4

 

12

RRM

 

m3

20

10

 
 

 

5.   PROGRAMME FOR NEXT WEEK

Sl No

Item / Work

Unit

Planned Quantity Next week

 
 

1

Earthwork Excavation

m3

1600

 

2

Loosening & Leveling

m3

280

 

3

Sub-grade

m3

550

 

4

GSB

m3

520

 

5

WMM

m3

200

 

6

Earthwork Excavation Culvert

m3

50

 

7

PCC M15

m3

3

 

8

Wing Wall M35

m3

5

 

9

HYSD Bar

kg

300

 

10

Site Clearance

ha

0.1

 

11

DRM

m3

15

 

12

RRM

m3

10

 
 

 

6.   MANPOWER STATEMENT FOR THE WEEK

SL.NO

DESIGNAITION

PRESENT

STAFF

PRESENT

Remarks

1

Carpenter

-

Project Manager

 

 

2

Mason

5

Asst. Project Manager

 

 

3

Steel Fixer

 

Site Engineer

1

 

4

Labour

15

Plant Engineer

 

 

5

Store Helper

 

QA/QC Engineer

 1

 

6

Electrician Helper

 

Quantity Surveyor

 

 

7

Site Security

 

Planner

 

 

8

Office Boy

 

Safety Officer

 

 

9

Tea Boy

 

Supervisors

2

 

10

Sweeper

 

Foreman

 

 

11

Safety Asst

 

Jnr. Foreman

 

 

12

Lab. Asst

 

Surveyor

 

13

Receptionist

 

Draughtsman

 

 

14

Document Controller

2

Secretary

 

 

15

Time Keeper

 

Store Keeper

 

 

16

Others

15

Others

 

 

 

TOTAL

37

 

6

 

 

7.   CONTRACTOR’S PLANT AND EQUIPEMNT SCHEDULE

SL.NO

MACHINERIES

OWN

HIRE

QTY

 SL.NO

MACHINERIES

OWN

HIRE

QTY

1

Concrete Plant

1

-

1

10

JCB

-

2

2

2

Concrete Pumps

-

-

 

11

Excavator

1

1

2

3

Vibrator

1

-

1

12

Pick Up

-

-

-

4

Crane

-

-

-

13

Hot Mix Plant

-

-

-

5

Truck/Tipper

2

3

5

14

Paver Finisher

-

-

-

6

Tanker

1

-

1

15

Bitumen Finisher

-

-

-

7

Roller (Vibratory)

1

1

2

16

Pilling RIG

-

-

-

8

Roller (Static)

-

-

-

17

Lab Test Equipment

-

-

-

9

Generator

-

-

-

18

Others

1

-

1

 

8.   QUALITY ASSURANCE / QUALITY CONTROL RECORDS

Sl No.

Item

Date submitted

Date Returned

Status

Remarks

1

NCR

-

-

-

-

2

Inspection requests

 

 

 

31 No.s

3

Calibration Certificates

 

 

 

 

4

Test Conducted

 

 

 

 

4a

FIELD COMPACTION

 

 

O.K

SUB-GRADE         ( 3 tests)

4b

FIELD COMPACTION

 

 

O.K

GSB( 3 tests)

4c

GRADATION

 

 

O.K

GSB( 1 test)

Any Other Quality Related Issues

 

 

 

9.   PROGRESS PHOTOGRAPHS(Attached)

 
Back
 
    
WMM

    
    
WMM

    
    
WMM

    
    
SUBGRADE PREPARATION

    
 
    
EARTH WORK EXCAVATION

      
 

 

 

 

 

 

 

 