WEEKLY REPORT |
|
|
|
|
|
|
|
|
|
Date:25/10/13 |
|
Name of Work: Strengthening,Widening, and Extension of Tippu Sulthan Road-PHASE-I Chainage :0.000 TO 4.50 KM |
Sl No |
Item / Work |
Location |
Unit |
Planned Quantity |
Executed quantity |
Total Executed quantity |
Planned Quantity Next week |
Remarks |
1 |
Earthwork Excavation |
2/140 - 2/830 RHS |
M3 |
1600 |
1920 |
5511 |
1700 |
|
2 |
Loosening&Levelling |
2/140 - 2/830 RHS |
M3 |
350 |
290 |
953 |
300 |
Work Obstructed due to Rain |
3 |
Subgrade |
2/270 - 2/830 RHS |
M3 |
700 |
580 |
1907 |
600 |
Work Obstructed due to Rain |
4 |
GSB |
2/270 - 2/830 RHS |
M3 |
640 |
510 |
1784 |
550 |
Work Obstructed due to Rain |
5 |
WMM |
3/450 - 3/690 |
M3 |
50 |
105 |
158 |
250 |
|
6 |
Dismantling CC |
1/722RHS |
M3 |
10 |
4 |
57.694 |
|
|
7 |
Earthwork Excavation Culvert |
1/722 RHS |
M3 |
75 |
65 |
1090 |
75 |
|
8 |
PCC M15 |
1/722 RHS |
M3 |
6 |
1.5 |
50.5 |
5 |
|
9 |
Wing Wall M35 |
|
M3 |
8 |
|
22 |
5 |
|
10 |
HYSD Bar |
|
KG |
400 |
|
15836 |
400 |
|
11 |
Site Clearance |
2/140 - 2/830 RHS |
Ha |
0.3 |
0.05 |
0.5 |
0.1 |
|
12 |
DRM |
|
M3 |
|
|
|
15 |
|
13 |
RRM |
|
M3 |
|
12 |
493 |
20 |
|
14 |
Erection of Culvert |
2/371,3/842,1/722,1/967 |
|
50%of3Nos |
50%of3Nos |
Completed |
|
Erection of all Culverts/ Utility Ducts Completed |
|
|