   weekly progress of 19-10-2013
    
  TIPPU SULTHAN ROAD Phase-I        
           
  WEEKLY PROGRESS REPORT  18OCT 2013      
           
  ITEM DESCRIPTION PROGRESS PROGRESS   PLANNING FOR NEXT WEEK
    THIS WEEK CUMULATIVE REMARKS  
           
1 EARTH WORK EXCAVATION 110.00M3 1015.00M3   75.00M3
  FOR CULVERT/RR WALL        
2 RRMASONRY WALL   481.00M3    
3 RCC PRE CAST M35   151.61M3    
  CULVERT/DUCT        
4 TREE PLANTING   220Nos.    
5 FENCING     Fabrication in Progress  
6 GUARD STONE CASTING   385Nos                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                  
7 EARTH WORK EXCAVATION 986M3 3591M3 CH2/830-CH3/120{RHS} 1600.00M3
  FOR ROAD WIDENING        
8 LOOSENING&RE COMPACTING 180.00m3 663M3 CH2/830-CH3/120{RHS} 663.00M3
9 SUB GRADE FILLING 360.00m3 1327.00M3 CH2/830-CH3/120{RHS} 700.00M3
10 GSB 350.00m3 1274.00M3 CH2/830-CH3/120{RHS} 640.00M3
11 WMM   53.00M3   50.00M3
12 PCC M15 5.00M3 49.00M3   6.00M3
13 RCC M35(wing wall) 2.00M3 22.00M3   8M3
14 REINFORCEMENT STEEL 0.166MT 15.836MT   0.40MT
15 TREE CUTTING   494Nos    
16 DISMANTLING RR MASONRY   78M3    
17 DISMANTLING CONCRETE 20.05M3 53.69M3   10.00M3
18 ERECTION OF CULVERT/DUCT 50%4Nos 10Nos   50%3Nos
           
 