TIPPU SULTHAN ROAD Phase-I |
|
|
|
|
|
|
|
|
|
|
|
WEEKLY PROGRESS REPORT |
18OCT 2013 |
|
|
|
|
|
|
|
|
|
|
ITEM DESCRIPTION |
PROGRESS |
PROGRESS |
|
PLANNING FOR NEXT WEEK |
|
|
THIS WEEK |
CUMULATIVE |
REMARKS |
|
|
|
|
|
|
|
1 |
EARTH WORK EXCAVATION |
110.00M3 |
1015.00M3 |
|
75.00M3 |
|
FOR CULVERT/RR WALL |
|
|
|
|
2 |
RRMASONRY WALL |
|
481.00M3 |
|
|
3 |
RCC PRE CAST M35 |
|
151.61M3 |
|
|
|
CULVERT/DUCT |
|
|
|
|
4 |
TREE PLANTING |
|
220Nos. |
|
|
5 |
FENCING |
|
|
Fabrication in Progress |
|
6 |
GUARD STONE CASTING |
|
385Nos |
|
|
7 |
EARTH WORK EXCAVATION |
986M3 |
3591M3 |
CH2/830-CH3/120{RHS} |
1600.00M3 |
|
FOR ROAD WIDENING |
|
|
|
|
8 |
LOOSENING&RE COMPACTING |
180.00m3 |
663M3 |
CH2/830-CH3/120{RHS} |
663.00M3 |
9 |
SUB GRADE FILLING |
360.00m3 |
1327.00M3 |
CH2/830-CH3/120{RHS} |
700.00M3 |
10 |
GSB |
350.00m3 |
1274.00M3 |
CH2/830-CH3/120{RHS} |
640.00M3 |
11 |
WMM |
|
53.00M3 |
|
50.00M3 |
12 |
PCC M15 |
5.00M3 |
49.00M3 |
|
6.00M3 |
13 |
RCC M35(wing wall) |
2.00M3 |
22.00M3 |
|
8M3 |
14 |
REINFORCEMENT STEEL |
0.166MT |
15.836MT |
|
0.40MT |
15 |
TREE CUTTING |
|
494Nos |
|
|
16 |
DISMANTLING RR MASONRY |
|
78M3 |
|
|
17 |
DISMANTLING CONCRETE |
20.05M3 |
53.69M3 |
|
10.00M3 |
18 |
ERECTION OF CULVERT/DUCT |
50%4Nos |
10Nos |
|
50%3Nos |
|
|
|
|
|
|
|
|