   weekly progress of 15-10-2013
    
         
  WEEKLY PROGRESS REPORT  13OCT 2013    
         
  ITEM DESCRIPTION PROGRESS PROGRESS  
    THIS WEEK CUMULATIVE  
         
1 EARTH WORK EXCAVATION 145.00M3 905.00M3  
  FOR CULVERT/RR WALL      
2 RRMASONRY WALL   481.00M3  
3 RCC PRE CAST M35   151.61M3  
  CULVERT/DUCT      
4 TREE PLANTING   220Nos.  
5 FENCING     Fabrication in Progress
6 GUARD STONE CASTING   385Nos                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                
7 EARTH WORK EXCAVATION   2605M3  
  FOR ROAD WIDENING      
8 LOOSENING&RE COMPACTING 232.00m3 483M3  
9 SUB GRADE FILLING 464.00m3 483M4  
10 GSB 432.00m3 924.00M3  
11 WMM 38.00m3 53.00M3  
12 PCC M15 8.00M3 44.00M3  
13 RCC M35(wing wall) 10.00M3 20.00M3  
14 REINFORCEMENT STEEL 0.39MT 15.67MT  
15 TREE CUTTING 59Nos 344Nos  
16 DISMANTLING RR MASONRY   78M3  
17 DISMANTLING CONCRETE   13.04M3  
 