   weekly progress of 17-09-2013
    
  TIPPU SULTHAN ROAD Phase-I      
         
  WEEKLY PROGRESS REPORT   15 SEPT 2013    
         
  ITEM DESCRIPTION PROGRESS PROGRESS  
    THIS WEEK CUMULATIVE  
         
1 EARTH WORK EXCAVATION   468.78M3  
  FOR CULVERT/RR WALL      
2 RRMASONRY WALL   481M3  
3 RCC PRE CAST M35   151.61M3  
  CULVERT/DUCT      
4 TREE PLANTING   220Nos.  
5 FENCING     Fabrication in Progress
6 GUARD STONE CASTING 169Nos 259Nos                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                
7 EARTH WORK EXCAVATION   17M3  
  FOR ROAD WORK      
8 GSB   108.00M3 Suppied 5650 M3
9 PCC M15   22.28M3  
10 TREE CUTTING 159Nos 215Nos  
11 DISMANTLING RR MASONRY   78M3  
12 DISMANTLING CONCRETE   13.04M3  
         
  Shifting&Erection of Culverts and Utility Ducts in progress  
 