TIPPU SULTHAN ROAD Phase-I |
|
|
|
|
|
|
|
|
|
WEEKLY PROGRESS REPORT |
15 SEPT 2013 |
|
|
|
|
|
|
|
|
ITEM DESCRIPTION |
PROGRESS |
PROGRESS |
|
|
|
THIS WEEK |
CUMULATIVE |
|
|
|
|
|
|
1 |
EARTH WORK EXCAVATION |
|
468.78M3 |
|
|
FOR CULVERT/RR WALL |
|
|
|
2 |
RRMASONRY WALL |
|
481M3 |
|
3 |
RCC PRE CAST M35 |
|
151.61M3 |
|
|
CULVERT/DUCT |
|
|
|
4 |
TREE PLANTING |
|
220Nos. |
|
5 |
FENCING |
|
|
Fabrication in Progress |
6 |
GUARD STONE CASTING |
169Nos |
259Nos |
|
7 |
EARTH WORK EXCAVATION |
|
17M3 |
|
|
FOR ROAD WORK |
|
|
|
8 |
GSB |
|
108.00M3 |
Suppied 5650 M3 |
9 |
PCC M15 |
|
22.28M3 |
|
10 |
TREE CUTTING |
159Nos |
215Nos |
|
11 |
DISMANTLING RR MASONRY |
|
78M3 |
|
12 |
DISMANTLING CONCRETE |
|
13.04M3 |
|
|
|
|
|
|
|
Shifting&Erection of Culverts and |
Utility Ducts in progress |
|
|
|