   weekly progress of 09-09-2013
    
TIPPU SULTHAN ROAD Phase-I      
       
WEEKLY PROGRESS REPORT    7 SEPT 2013    
       
ITEM DESCRIPTION PROGRESS PROGRESS  
  THIS WEEK CUMULATIVE  
       
EARTH WORK EXCAVATION 22M3 177M3  
FOR CULVERT/RR WALL      
RRMASONRY WALL   481M3  
RCC PRE CAST M35 0.50M3 151.61M3  
CULVERT/DUCT      
TREE PLANTING   220Nos.  
FENCING     Fabrication in Progress
GUARD STONE CASTING 90Nos. 90Nos.                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                
EARTH WORK EXCAVATION   17M3  
FOR ROAD WORK      
GSB 3.00M3 108.00M3 Suppied 5367 M3
PCC M15 1.31M3 22.28M3  
TREE CUTTING 26Nos 56Nos  
DISMANTLING RR MASONRY   78M3  
DISMANTLING CONCRETE 4.08M3 13.04M3  
       
 