   weekly progress of 30-08-2013
    
  TIPPU SULTHAN ROAD Phase-I        
           
  PROGRESS-Aug 2013        
           
  ITEM DESCRIPTION TARGET ACTUAL EXECUTED TARGET  
    AUGUST AUGUST SEPTEMBER  
           
1 EARTH WORK EXCAVATION 85M3 155M3 280M3  
  FOR CULVERT/RR WALL        
2 RRMASONRY WALL 45M3      
3 RCC PRE CAST M35 55M3 55.20M3    
  CULVERT/DUCT        
4 TREE PLANTING 250Nos. 220Nos.    
5 FENCING 500Nos.   500Nos.  
6 GUARD STONE 150Nos   500Nos.  
7 EARTH WORK EXCAVATION 800M3   3000M3  
  FOR ROAD WORK        
8 SUB GRADE 500M3   2000M3  From CH 2/000-3/600
9 GSB 500M3 15M3 2000M3 From CH 2/000-3/600
10 WMM 400M3   400M3 From CH 3/000-3/600
11 PCC M15 40M3 22M3 30M3  
12 RCC M35 FOR WING WALL     10M3  
13 DR MASONRY     100M3  
14 TREE CUTTING   30Nos 720Nos Completed CH 3/000-4/500
 
Back
 
    
BOX CULVERT READY FOR ERECTION

    
    
SHIFTING OF BOX CULVERT

    
    
CASTING YARD

    
    
WORK SITE

    
 
    
PCC FOR DRAINAGE CULVERT

    
    
PCC FOR UTILITY CULVERT

    
    
MECHANICAL EXCAVATION

    
 
    
EARTH WORK EXCAVATION

      
 

 

 

 

 

 

 

 

Untitled Document