   Weekly progress report as on 17.01.2014
    
Progress Report For Mooledam ROB for the week ending on 17-1-2014  
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE 21 21 0 0 0 0 0 0 0 Piling works completed
2 PILE CAP 7 7 0 0 0 0 0 0 0 Pile cap completed
3 PIER 9 9 0 0 0 0 0 0 0 Pier completed
4 PIER CAP 9 9 0 0 0 0 0 0 0 Pier cap completed
5 LOAD TEST 1 1 0 0 0 0 0 0 0 Load test completed 
6 ABUTMENT 2 2 0 0 0 0 0 0 0  
7 FOOTING 2 2 0 0 0 0 0 0 0  
8 GIRDER 9 9 0 0 0 0 0 0 0 Girder completed
9 DECK SLAB 9 9 0 0 0 0 0 0 0 Deck slab completed
10 PEDESTAL 11 11 0 0 0 0 0 0 0 Pedestal completed
11 RETAINING WALL  4 2 2.5 0 0.5 0.5 0 0.5 0 Manipuzha  RHS and LHS side work completed upto raft and deevan kavala LHS side upto wall
12 KERB 9 9 0 0 0 0 0 0 0  
13 EXPANSION JOINTS 7 7 0 0 0 0 0 0 0  
14 ADJACENT SPAN 2 0 0 0 0 0 0 0 0 Staging work started at manipuzha side
                       
 