Prevoius Weekly Reports

   Weekly progress report as on 10.01.2014
    
Progress as on 10-01-14
  Description Completed/ Progress Remarks
  ROB Kainatty (P6-RP4)    
1 Levelling and consolidation of the ground for staging work completed  
2 Staging work completed  
3 Reinforcement bending work completed  
4 Bottom shuttering work for girder completed  
5 Reinforcement binding for girder completed  
6 Shuttering work for girder completed  
7 Concreting of girder completed  
8 Shuttering work for deck slab completed  
9 Reinforcement binding of deck slab completed  
10 Deck slab concrete completed  
11 MISCELLANEOUS WORK In progress  
11(a) Concreting of kerb, handrails In progress Handrail fixing work started
11(b) Expansion joints completed  
12 ROAD WORK AND DRAINAGE Not started Drainage is built in the P6- Rp4  span area near staircase foundations
12(a) Aplplying mastic Asphault Not started  
12(b) Applying bituminous concrete Not started  
13 PAINTING WORK Not started  
 
  Description Completed/ Progress Remarks
  ROB Kainatty (P5-RP1)    
1 Levelling and consolidation of the ground for staging work completed  
2 Staging work completed  
3 Reinforcement bending work completed  
4 Bottom shuttering work for girder completed  
5 Reinforcement binding for girder completed  
6 Shuttering work for girder completed  
7 Concreting of girder completed  
8 Shuttering work for deck slab completed  
9 Reinforcement binding of deck slab completed  
10 Deck slab concrete completed  
11 MISCELLANEOUS WORK In progress  
11(a) Concreting of kerb, handrails In progress Handrail fixing work started
11(b) Expansion joints completed  
12 ROAD WORK Not started  
12(a) Aplplying mastic Asphault Not started  
12(b) Applying bituminous concrete Not started  
13 PAINTING WORK Not started  
       
  Description Completed/ Progress Remarks
  STAIRCASE-NADAPURAM  EAST SIDE    
1 Earthwork in excavation completed  
2 P.C.C for foundation completed  
3  Concreting of foundations completed  
4 Concreting of columns completed  
5 Concreting of flights completed  
       
  Description Completed/ Progress Remarks
  STAIRCASE-NADAPURAM  WEST SIDE    
1 Earthwork in excavation completed  
2 P.C.C for foundation completed  
3  Concreting of foundations completed  
4 Concreting of columns completed  
5 Concreting of flights completed  
       
  STAIRCASE-KAINATTY  EAST SIDE    
1 Earthwork in excavation In progress  
2 P.C.C for foundation Not started  
3  Concreting of foundations Not started  
4 Concreting of columns Not started  
5 Concreting of flights Not started  
       
 
Back