Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 8051267
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   3/12/2010
    

 

Progress Report For Kainatty ROB for the week ending on 03-12-2010
Si No
Activity Description
Total Quantity
Cumulative progress upto this week
Balance  work
Cumulative delay in weeks
Work  planned  during the week
Actual work done during the week
Delay for the week  
Work  Planned for next week
Remarks
1
PILE KAINATTY  SIDE
18
7
11
0
3
2
0
0
 
2
PILE NADAPURAM SIDE
27
1
26
0
0
0
0
3
 
3
PILE CAP KAINATTY SIDE
6
0
6
0
0
0
0
1
 
4
PILE CAP  NADAPURAM SIDE
9
0
9
0
0
0
0
0
 
5
PIER KAINATTY  SIDE
6
0
6
0
0
0
0
0
 
6
PIER NADAPURAM SIDE
9
0
9
0
0
0
0
0
 
7
PIER CAP KAINATTY  SIDE
6
0
6
0
0
0
0
0
 
8
PIER CAP NADAPURAM SIDE
9
0
9
0
0
0
0
0
 
9
RE/R WALL KAINATTY  SIDE
100%
0
100%
0
0.00%
0.00%
0.00%
0.00%
 
10
RE/R WALL NADAPURAM SIDE
100%
0
100%
0
0.00%
0.00%
0.00%
0.00%
 
 
Back
 
    
CONCRETING OF P1(B) (02/12/2010)

    
    
BORING OF PILE P8 (A)

    
    
WOODEN PIECES STACKED AFTER CUTTING (30/11/2010)

    
    
CUTTING OF TREE (28/11/2010)

    
 
    
TRIPOD SETTING (28/11/2010)

    
    
CONCRETING OF P1(A) (28/11/2010)

      
 

 

 

 

 

 

 

 

Untitled Document