   Weekly progress report as on 03.01.2014
    
PROGRESS OF ROB MULAMKUNNATHUKAVU (Adjacent spans) AS ON 03.01.2014
  Description Completed/ Progress Remarks
       
  Medical College side:    
1 Girder 4 No.s casting Completed  
2 Deck slab Shuttering Completed  
3 Deck slab Reinforcement works Completed  
4 Casting of RP2-P3 Deck slab Completed  
5 Casting of kerbs In progress  
6 Stair case   Work in progress
       
  NH side    
1 Casting of slabs for staging Completed  
2 Staging works Completed  
3 RP1-P2 girder ( 4 No.s) Completed  
4 RP1-P2 deck slab Completed  
       
  Toll booth Stopped Work stopped due to protest
  Stair case excation Completed  
       
       
       
       
 