Progress Report For Palakkad Sultanpet ROB for the week ending on 03.01.2014 |
Si No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
No of days remaing for completion as per the weekly plan |
Remarks |
1 |
PCC for RAFT MOYAN SIDE |
3 |
3 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
2 |
PCC for RAFT PALAKKAD SCHOOL SIDE |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
3 |
RAFT PALAKKAD SIDE |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
4 |
RAFT MOYAN SCHOOL SIDE |
3 |
3 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
5 |
PIER PALAKKAD SIDE |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
6 |
PIER MOYAN SCHOOL SIDE |
3 |
3 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
7 |
PIER CAP PALAKKAD SIDE |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
8 |
PIER CAP MOYAN SCHOOL SIDE |
3 |
3 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
9 |
RE/R WALL PALAKKAD SIDE |
100% |
100% |
0% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
10 |
RE/R WALL MOYAN SCHOOL SIDE |
100% |
100% |
0% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
11 |
BEAM/SLAB Staging Palakad SIDE |
2 |
2 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
12 |
BEAM/SLAB Bar bending and Fixing Palakad SIDE |
2 |
2 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
13 |
BEAM/SLAB Shuttering and Concreting Palakad SIDE |
2 |
2 |
0 |
0 |
0 |
0 |
0 |
o |
|
|
14 |
BEAM/SLAB Staging Moyan schoolSIDE |
4 |
4 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
15 |
BEAM/SLAB Bar bending and Fixing Moyan school SIDE |
4 |
4 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
16 |
BEAM/SLAB Shuttering and Concreting Moyan school SIDE |
4 |
4 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
17 |
BEAM/SLAB PALAKKAD SIDE |
2 |
2 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
18 |
BEAM/SLAB MOYAN SCHOOL SIDE |
4 |
4 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
19 |
BEAM/SLAB RAILWAY SPAN |
6 |
5 |
1 |
0 |
0 |
0 |
0 |
0 |
|
|
20 |
HR/FP/KERB Pkd SIDE |
100% |
100% |
0% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
21 |
HR/FP/KERB Moyen's SIDE |
100% |
100% |
0% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
22 |
HR/FP/KERB RAILWAY SPAN |
100% |
76% |
24% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
23 |
BC/PAINTING |
100% |
60% |
40% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Note: Progress review done based on the revised Program (rev-01) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
ROB Sulthanpet, Palakkad |
|
|
|
|
|
|
|
|
|
|
|
Date |
Painters |
Erection works |
Helpers/Mechanics |
|
|
|
|
|
|
|
|
21/12/2013 |
|
6 |
10 |
|
|
|
|
|
|
|
|
22/12/2013 |
|
5 |
5 |
|
|
|
|
|
|
|
|
23/12/2013 |
|
6 |
10 |
|
|
|
|
|
|
|
|
24/12/2013 |
|
5 |
5 |
|
|
|
|
|
|
|
|
25/12/2013 |
|
3 |
5 |
|
|
|
|
|
|
|
|
26/12/2013 |
|
4 |
5 |
|
|
|
|
|
|
|
|
27/12/2013 |
|
6 |
5 |
|
|
|
|
|
|
|