Prevoius Weekly Reports

   03/12/10
    
Progress Report For Parappanangadi ROB for the week ending on 03-12-2010
Si No  Activity Description  Total Quantity Cumulative progress upto this week  Balance  work  Cumulative delay in weeks  Work  planned  during the week  Actual work done during the week  Delay for the week    Work  Planned for next week  Remarks 
1 PILE CALICUT  SIDE 30 0 30 0 0 0 0 3  
2 PILE NH SIDE 33 27 6 0 0 4 0 6  
3 PILE RAILWAY SPAN 20 0 20 0 0 0 0 0  
4 PILE CAP CALICUT  SIDE 10 0 10 0 0 0 0 0  
5 PILE CAP NH SIDE 11 0 11 1 0 0 3 1  
6 PILE CAP RAILWAY SPAN 4 0 4 0 0 0 0 0  
                     
Note: Progress review done based on the revised Program (rev-01)        
 
Back
 
    
PREPARATION FOR PILE LOAD TEST (1.12.2010)

    
    
CONCRETING OF PILE P12-A(29.11.2010)

    
    
CONCRETING OF PILE P11-C(1.12.2010)

    
    
CONCRETING OF PILE P11-A(29.11.2010)

    
 
    
CONCRETING OF PILE P15-B(26.11.2010)

    
    
CONCRETING OF PILE P12-B(26.11.2010)

      
 

 

 

 

 

 

 

 