   Weekly progress report as on 13.12.2013
    
PROGRESS OF ROB ALOOR-MALA  WORK AS ON 13-12-2013.
  Description Completed/ Progress Remarks
1 ROB ALOOR-MALA    
1 Piling Completed. completed 32/32
2 Pilecap In Progress COMPLETED 5OUT OF 8
3 Pier In Progress completed 3.out of 8.
4 Piercap In Progress P2 in progress.
5 Girder Not started  
6 Slab Not started  
7 Handrail with kerb Not started  
8 Ex.joint Not started  
9 Tarring work Not started  
10 Service road work  In Progress aloor right side in progress 100% completed.Mala side LHS 100%
11 Retaining wall work Not started  
12 Load test . Completed. In P4 location.
       
       
       
       
       
       
       
 
Back