   26.11.2010
    

 

 

RBDCK Engineer-Shri Ajaykrishnan, Contact No. 9745319841

KITCO Engineer - Shri Binu Lazar, Contact No.9446278195

GPT Engineer - Shri Sunny Pulikal, Contact No.9388085153

 

Progress Report For Palakkad Sultanpet ROB for the week ending on 26-11-2010

Si No  Activity Description  Total Quantity Cumulative progress upto this week  Balance  work  Cumulative delay in weeks  Work  planned  during the week  Actual work done during the week  Delay for the week    Work  Planned for next week  Remarks 
1 PCC for RAFT PALAKKAD SIDE 1 0 1 14 0 0 1 0  
2 PCC for RAFT MOYAN SCHOOL SIDE 3 0 3 13 0 8 3 0  
4 RAFT PALAKKAD SIDE 1 0 1 12 0 0 1 0  
5 RAFT MOYAN SCHOOL SIDE 3 0 3 12 0 0 3 0  
7 PIER PALAKKAD SIDE 1 0 1 11 0 0 1 0  
8 PIER MOYAN SCHOOL SIDE 3 0 3 10 0 0 3 0  
10 PIER CAP PALAKKAD SIDE 1 0 1 9 0 0 1 0  
11 PIER CAP MOYAN SCHOOL SIDE 3 0 3 8 0 0 3 0  
13 RE/R WALL PALAKKAD  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
14 RE/R WALL MOYAN SCHOOL SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
16 BEAM/SLAB PALAKKAD  SIDE 2 0 2 0 0 0 0 0  
17 BEAM/SLAB MOYAN SCHOOL SIDE 4 0 4 2 0 0 1 0  
18 BEAM/SLAB RAILWAY SPAN 7 0 7 2 0 0 1 0  
19 HR/FP/KERB CALICUT  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
20 HR/FP/KERB NH SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
21 HR/FP/KERB RAILWAY SPAN 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
22 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
 