Sl. No. |
BOQ REF |
Item Description |
Unit |
Total Quantity |
Cumulative progress upto November 31 |
Balance work up to November 31 |
1 |
1.01 |
Clearing and grubbing road land |
HA |
3.9 |
1.49 |
2.41 |
2 |
1.03 |
Dismantling of existing structures (Rubble masonry) |
Cum |
100 |
31.07 |
68.93 |
3 |
1.04 |
Dismantling of existing structures (block/brick) |
|
|
|
Cum |
50 |
7.70 |
42.30 |
4 |
1.05 |
Dismantling sign boards with foundation concrete, backfilling |
|
|
|
Cum |
60 |
2.10 |
57.90 |
5 |
1.09 |
Excavation for roadway |
Cum |
1320 |
360.00 |
960.00 |
6 |
1.10 |
Earthwork excavation at embankment foundation |
|
|
|
Cum |
30210 |
14.08 |
30195.92 |
7 |
1.11 |
Loosening, leveling and Compacting |
|
|
|
Cum |
1240 |
68.03 |
1171.97 |
8 |
1.13 |
GSB (Grade I) |
Cum |
8050 |
0.00 |
8050.00 |
9 |
1.25 |
Construction of embankment with approved material |
|
|
|
Cum |
1080 |
0.00 |
1080.00 |
10 |
1.26 |
Construction of embankment with red earth |
|
|
|
Cum |
200 |
59.25 |
140.75 |
11 |
1.27 |
Construction of embankment (road way cutting material) |
|
|
|
Cum |
3890 |
0.00 |
3890.00 |
12 |
1.28 |
PCC M15 for sub-structure - for culverts , drain, utility duct etc |
|
|
|
Cum |
1050 |
38.44 |
1011.56 |
13 |
1.29 |
PCC M25 for sub-structure/super structure etc for culverts , drain, utility duct |
|
|
|
Cum |
5070 |
0.00 |
5070.00 |
14 |
1.30 |
HYSD bar reinforecemnt in sub -structure |
|
|
|
MT |
510 |
0.00 |
510.00 |
15 |
1.36 |
M20 grade concrete guard posts 200 x 200 mm x1.25 m |
|
|
|
Nos |
550 |
27.00 |
523.00 |