Prevoius Weekly Reports

   Weekly progress report as on 06.12.2013
    
PROGRESS OF ROB MULAMKUNNATHUKAVU (Adjacent spans) AS ON 06-12-2013
  Description Completed/ Progress Remarks
       
  Medical College side:    
1 Girder 4 No.s casting Completed  
2 Deck slab Shuttering Completed  
3 Deck slab Reinforcement works Completed  
4 Casting of RP2-P3 Deck slab Completed  
5 Casting of kerbs In progress  
6 Stair case   Work will start after railway contractor
      removes the cribs from the location
  NH side    
1 Casting of slabs for staging Completed  
2 Staging works Completed  
3 RP1-P2 girder ( 2 No.s) Completed  
4 RP1-P2 girder ( 2 No.s) In progress Casting on 7/12/13
       
  Toll booth Stopped Work stopped due to protest
       
       
       
       
       
       
       
       
       
       
       
       
 
Back
 
    
STEEL RNFT OF GIRDERS 3 & 4

    
    
CASTING OF GIRDER 1 &2 OF RP1-P2

      
 

 

 

 

 

 

 

 