|
PROGRESS OF ROB ALOOR-MALA WORK AS ON 29-11-2013. |
|
Description |
Completed/ Progress |
Remarks |
1 |
ROB ALOOR-MALA |
|
|
1 |
Piling |
Completed. |
completed 32/32 |
2 |
Pilecap |
In Progress |
P1,P2,P3 COMPLETED,P6 IN PROGRESS. |
3 |
Pier |
In Progress |
completed P2,P1. |
4 |
Piercap |
In Progress |
P2 STARTED. |
5 |
Girder |
Not started |
|
6 |
Slab |
Not started |
|
7 |
Handrail with kerb |
Not started |
|
8 |
Ex.joint |
Not started |
|
9 |
Tarring work |
Not started |
|
10 |
Service road work |
In Progress |
aloor right side in progress 100% completed.Mala side LHS 90% |
11 |
Retaining wall work |
Not started |
|
12 |
Load test completed. |
Completed. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|