CONSTRUCTION OF ROB AT KAINATTI |
Programme commited |
NOVEMBER- 2013 |
SL. No. |
ACTIVITY PLANNED |
ACTIVITY ACHIEVED |
SHORT FALL |
REMARKS/ REASON |
|
P6-RP4 SIDE |
|
|
|
1 |
Miscellaneous work |
80% |
20% |
kebs and expansion joint completed |
|
|
|
|
|
|
P5-RP1 SIDE |
|
|
|
1 |
Reinforcement binding and shuttering work for girder |
100% |
NIL |
|
2 |
Girder concrete |
100% |
NIL |
|
3 |
Shuttering and steel work for deck slab |
100% |
NIL |
|
4 |
Deck slab concrete |
100% |
NIL |
|
5 |
Miscellaneous work |
80% |
20% |
kebs and expansion joint completed |
|
staircase-nadapuram east side |
|
|
|
1 |
Earth work in excavation |
100% |
NIL |
|
2 |
concreting of foundation |
100% |
NIL |
|
|
|
|
|
|
|
staircase-nadapuram west side |
|
|
|
1 |
Earth work in excavation |
100% |
NIL |
|