Prevoius Weekly Reports

   19.11.2010
    

 RBDCK Engineer-Radhakrishnan, Contact No.9447178783

KITCO Engineer - Santhosh.G, Contact No. 9447384217

GPT Engineer - Nikhil, Contact No. 9539007550

 

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work

Cumulative delay in weeks

Work  planned  during the week

Actual work done during the week

Delay for the week

 Work  Planned for next week

Remarks

1

PILE SHORNUR SIDE

9

0

9

5

 0

 

 

 

 

2

PILE MED. COLLEGE SIDE

36

19

10

5

8

7

1

8

 

3

PILE RAILWAY SPAN

6

 

6

11

0

0

0

 

 

4

PILE CAP SHORNUR SIDE

3

 

3

5

0

0

0

 

 

5

PILE CAP MED. COLLEGE SIDE

15

 

15

3

0

0

0

 

 

6

PILE CAP RAILWAY SPAN

2

 

2

5

0

0

0

 

 

 
Back
 
    
ERECTION OF REINFORCEMENT FOR PILE.JPG

    
    
P12 B PILE CONCRETING .JPG

    
    
EARTH REMOVING FOR PILE CAP

    
    
P10 C PILE CONCRETING

    
 
    
MATERIALS LOADING FOR PILE LOAD TEST

    
    
PCC FOR PILE CAP

      
 

 

 

 

 

 

 

 