Sl No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
Remarks |
1 |
PILE CHERUVATHOOR SIDE |
27 |
27 |
Completed |
|
2 |
PILE PADANNA SIDE |
24 |
24 |
Completed |
|
3 |
PILE CAP CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
4 |
PILE CAP PADANNA SIDE |
8 |
8 |
Completed |
|
5 |
PIER CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
6 |
PIER PADANNA SIDE |
8 |
8 |
Completed |
|
7 |
PIER CAP CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
8 |
PIER CAP PADANNA SIDE |
8 |
8 |
Completed |
|
9 |
RE/RC WALL CHERUVATHOOR SIDE |
100% |
100% |
Completed |
Friction slab and capping complete at both sides. |
10 |
RE/RC WALL PADANNA SIDE |
100% |
100% |
Completed |
Friction slab capping complete at both RHS&LHS. |
11 |
BEAM/SLAB CHERUVATHOOR SIDE |
9 |
8 |
1 |
complete except railway adjacent span |
|
12 |
BEAM/SLAB PADANNA SIDE |
8 |
7 |
1 |
complete except railway adjacent span |
|
13 |
EXPANSION JOINT CHERUVATHUR SIDE |
9 |
8 |
1 |
0 |
0 |
0 |
0 |
0 |
complete except P8 |
14 |
EXPANSION JOINT PADANNA SIDE |
8 |
7 |
1 |
0 |
0 |
0 |
0 |
0 |
complete except P7 |
15 |
KERB CHERUVATHOOR SIDE |
100% |
100.00% |
Completed |
complete for Friction slab also. |
16 |
KERB PADANNA SIDE |
100% |
100% |
Completed |
complete for RE Panel portion also. |
17 |
HANDRAIL CHERUVATHUR SIDE |
100% |
100% |
Completed |
complete for RE Panel portion also. |
18 |
HANDRAIL PADANNA SIDE |
100% |
100% |
Completed |
complete for RE Panel portion also. |
19 |
Painting |
100% |
75% |
25% |
10% |
10% |
0% |
10% |
10% |
Painting works again held up due to lack of labour. |
17 |
BM/BC |
100% |
80% |
20% |
20% |
20.00% |
10.00% |
10.00% |
10.00% |
Bitumen works complete except Padanna side 4m road since drainage cover slab casting is not complete. |
18 |
Others/Miscellaneous |
|
|
|
|
|
|
|
|
Drainage works complete for 150 m at chr side. |
19 |
ROAD WORK |
GSB+WMM Work 100% complete |
|
20 |
Drainage Padanna side |
100.00% |
70.00% |
30.00% |
40.00% |
30.00% |
20.00% |
10.00% |
10.00% |
Drainage cover slab casting 50% complete.Cross drainage second half remaining. |
|
|
|
|
|
|
|
|
|
|
DR Work complete for 4m service road and 7m road chr side. |
21 |
RAILWAY PORTION |
|
|
|
|
|
|
|
|
RP3 PIER CAP COMPLETE,RP2 PIER 2ND LIFT COMPLETE,RP1 PILE CAP WORK IP. |
|
|
|
|
|
|
|
|
|
|
Hume pipe laying complete at chr side to drain off rain water |
|
|
|
|
|
|
|
|
|
|
|
|
Availbility of Men |
|
|
|
|
|
|
|
|
|
|
Date |
11/16/2013 |
11/17/2013 |
11/18/2013 |
11/19/2013 |
11/20/2013 |
11/21/2013 |
11/22/2013 |
|
|
|
No of labours |
20 |
20 |
20 |
20 |
20 |
20 |
20 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Material Stocking Status |
Required |
Available |
Remarks |
|
|
|
|
|
|
|
Coarse Aggreagate (m3) |
available |
|
|
|
|
|
|
|
|
Fine Aggreagate(m3) |
available |
|
|
|
|
|
|
|
Cement(bag) |
80 |
100 |
|
|
|
|
|
|
|
Steel(MT) |
1 |
2 |
|
|
|
|
|
|