   Weekly progress report as on 15.11.2013
    
PROGRESS OF ROB ALOOR-MALA  WORK AS ON 15-11-2013.
  Description Completed/ Progress Remarks
1 ROB ALOOR-MALA    
1 Piling Progress completed 32/32
2 Pilecap Progress P1,P2 COMPLETED,P3,P6 IN PROGRESS.
3 Pier Not started completed p2,P1.
4 Piercap Not started P2 STARTED.
5 Girder Not started  
6 Slab Not started  
7 Handrail with kerb Not started  
8 Ex.joint Not started  
9 Tarring work Not started  
10 Service road work Progress aloor right side in progress 90% completed.
11 Retaining wall work Not started  
       
       
       
       
       
       
       
       
 
Back
 
    
P6 PCC .

    
    
P3 PILECAP WORK.

    
    
P1,P2 PIER

    
    
LOAD TESTING ARRANGEMENTS STARTED.

    
 
 
 

 

 

 

 

 

 

 