Prevoius Weekly Reports

   Weekly progress report as on 15.11.2013
    
Progress as on 15-11-13
  Description Completed/ Progress Remarks
  ROB Kainatty (P6-RP4)    
1 Levelling and consolidation of the ground for staging work completed  
2 Staging work completed  
3 Reinforcement bending work completed  
4 Bottom shuttering work for girder completed  
5 Reinforcement binding for girder completed  
6 Shuttering work for girder completed  
7 Concreting of girder completed  
8 Shuttering work for deck slab completed  
9 Reinforcement binding of deck slab completed  
10 Deck slab concrete completed  
11 MISCELLANEOUS WORK In progress  
11(a) Concreting of kerb, handrails Started Kerb completed(90%)
11(b) Expansion joints Started  
12 ROAD WORK Not started  
12(a) Aplplying mastic Asphault Not started  
12(b) Applying bituminous concrete Not started  
13 PAINTING WORK Not started  
 
  Description Completed/ Progress Remarks
  ROB Kainatty (P5-RP1)    
1 Levelling and consolidation of the ground for staging work completed  
2 Staging work completed  
3 Reinforcement bending work completed  
4 Bottom shuttering work for girder completed  
5 Reinforcement binding for girder completed  
6 Shuttering work for girder completed  
7 Concreting of girder completed  
8 Shuttering work for deck slab completed  
9 Reinforcement binding of deck slab completed  
10 Deck slab concrete completed  
11 MISCELLANEOUS WORK Started  
11(a) Concreting of kerb, handrails Started Kerb completed(90%)
11(b) Expansion joints Started  
12 ROAD WORK Not started  
12(a) Aplplying mastic Asphault Not started  
12(b) Applying bituminous concrete Not started  
13 PAINTING WORK Not started  
 