Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 8053435
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly Progress Report as on 15.11.2013
    
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  Remarks 
1 PILE CHERUVATHOOR  SIDE 27 27 Completed  
2 PILE PADANNA SIDE 24 24 Completed  
3 PILE CAP CHERUVATHOOR SIDE 9 9 Completed  
4 PILE CAP  PADANNA SIDE 8 8 Completed  
5 PIER CHERUVATHOOR SIDE 9 9 Completed  
6 PIER PADANNA SIDE 8 8 Completed  
7 PIER CAP CHERUVATHOOR SIDE 9 9 Completed  
8 PIER CAP PADANNA SIDE 8 8 Completed  
9 RE/RC WALL CHERUVATHOOR  SIDE 100% 100% Completed Friction slab and capping complete at both sides.
10 RE/RC  WALL PADANNA SIDE 100% 100% Completed Friction slab capping complete at both RHS&LHS.
11 BEAM/SLAB CHERUVATHOOR  SIDE 9 8 1 complete except railway adjacent span  
12 BEAM/SLAB PADANNA SIDE 8 7 1 complete except railway adjacent span  
13 EXPANSION JOINT CHERUVATHUR SIDE 9 8 1 0 0 0 0 0 complete except P8
14 EXPANSION JOINT PADANNA SIDE 8 7 1 0 0 0 0 0 complete except P7
15 KERB CHERUVATHOOR  SIDE 100% 100.00% Completed complete for Friction slab also.
16 KERB PADANNA SIDE 100% 100% Completed complete for RE Panel portion also.
17 HANDRAIL CHERUVATHUR SIDE 100% 100% Completed complete for RE Panel portion also.
18 HANDRAIL PADANNA SIDE 100% 100% Completed complete for RE Panel portion also.
19 Painting 100% 75% 25% 10% 10% 0% 10% 10% Painting restarted at cheruvathur side today.
17 BM/BC 100% 65% 35% 35% 20.00% 15.00% 10.00% 20.00% chr side 100% complete,Padanna side 4m road remaining.
18 Others/Miscellaneous                 Drainage works complete for 150 m at chr side.
19 ROAD WORK GSB+WMM Work 100% complete  
20 Drainage Padanna side 100.00% 50.00% 50.00% 40.00% 30.00% 20.00% 10.00% 30.00% Drainage wall concreted for 130m.Cover slab work IP.Cross drainage raft concreted.
                    DR Work complete for 4m service road and 7m road chr side.
21 RAILWAY PORTION                 RP3 PIER CAP COMPLETE,RP2 PILE CAP COMPLETE,RP1 PILE CAP WORK IP.
                    Hume pipe laying complete at chr side to drain off rain water
 
Back
 
    
PADANNA SIDE

    
    
CHR SIDE PAINTING WORKS STARTED

      
 

 

 

 

 

 

 

 

Untitled Document