Sl No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
Remarks |
1 |
PILE CHERUVATHOOR SIDE |
27 |
27 |
Completed |
|
2 |
PILE PADANNA SIDE |
24 |
24 |
Completed |
|
3 |
PILE CAP CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
4 |
PILE CAP PADANNA SIDE |
8 |
8 |
Completed |
|
5 |
PIER CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
6 |
PIER PADANNA SIDE |
8 |
8 |
Completed |
|
7 |
PIER CAP CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
8 |
PIER CAP PADANNA SIDE |
8 |
8 |
Completed |
|
9 |
RE/RC WALL CHERUVATHOOR SIDE |
100% |
100% |
Completed |
Friction slab and capping complete at both sides. |
10 |
RE/RC WALL PADANNA SIDE |
100% |
100% |
Completed |
Friction slab capping complete at both RHS&LHS. |
11 |
BEAM/SLAB CHERUVATHOOR SIDE |
9 |
8 |
1 |
complete except railway adjacent span |
|
12 |
BEAM/SLAB PADANNA SIDE |
8 |
7 |
1 |
complete except railway adjacent span |
|
13 |
EXPANSION JOINT CHERUVATHUR SIDE |
9 |
8 |
1 |
0 |
0 |
0 |
0 |
0 |
complete except P8 |
14 |
EXPANSION JOINT PADANNA SIDE |
8 |
7 |
1 |
0 |
0 |
0 |
0 |
0 |
complete except P7 |
15 |
KERB CHERUVATHOOR SIDE |
100% |
100.00% |
Completed |
complete for Friction slab also. |
16 |
KERB PADANNA SIDE |
100% |
100% |
Completed |
complete for RE Panel portion also. |
17 |
HANDRAIL CHERUVATHUR SIDE |
100% |
100% |
Completed |
complete for RE Panel portion also. |
18 |
HANDRAIL PADANNA SIDE |
100% |
100% |
Completed |
complete for RE Panel portion also. |
19 |
Painting |
100% |
75% |
25% |
10% |
10% |
0% |
10% |
10% |
Painting restarted at cheruvathur side today. |
17 |
BM/BC |
100% |
65% |
35% |
35% |
20.00% |
15.00% |
10.00% |
20.00% |
chr side 100% complete,Padanna side 4m road remaining. |
18 |
Others/Miscellaneous |
|
|
|
|
|
|
|
|
Drainage works complete for 150 m at chr side. |
19 |
ROAD WORK |
GSB+WMM Work 100% complete |
|
20 |
Drainage Padanna side |
100.00% |
50.00% |
50.00% |
40.00% |
30.00% |
20.00% |
10.00% |
30.00% |
Drainage wall concreted for 130m.Cover slab work IP.Cross drainage raft concreted. |
|
|
|
|
|
|
|
|
|
|
DR Work complete for 4m service road and 7m road chr side. |
21 |
RAILWAY PORTION |
|
|
|
|
|
|
|
|
RP3 PIER CAP COMPLETE,RP2 PILE CAP COMPLETE,RP1 PILE CAP WORK IP. |
|
|
|
|
|
|
|
|
|
|
Hume pipe laying complete at chr side to drain off rain water |