PROGRESS OF ROB MULAMKUNNATHUKAVU (Adjacent spans) AS ON 08-11-2013 |
|
Description |
Completed/ Progress |
Remarks |
|
|
|
|
|
Medical College side: |
|
|
1 |
Girder 4 No.s casting |
Completed |
|
2 |
Deck slab Shuttering |
Completed |
|
3 |
Deck slab Reinforcement works |
Completed |
|
4 |
Casting of RP2-P3 Deck slab |
Completed |
|
5 |
Casting of kerbs |
In progress |
|
|
|
|
|
|
NH side |
|
|
1 |
Casting of slabs for staging |
Completed |
|
2 |
Staging works |
In progress |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|