Prevoius Weekly Reports

   weekly progress as on 1.11.2013
    

 

  

Sl No 

Activity Description 

Total Quantity

Cumulative progress upto 1.11.2013

Balance  work up to 1.11.2013

Cumulative delay in Qty up to 1.11.2013

Work  planned  during the week 

Actual work done during the week 

Delay in Qty up to this week

Work  Planned for next week 

1

SLAB Pettah side(Approach portion)

4

4

0

 

 

 

 

 

2

SLAB Anayara side(Approach portion)

4

4

0

 

 

 

 

 

3

Service Road Pettah side(Approach portion)

100%

100%

0

 

 

 

 

 

4

Service Road Anayara side(Approach portion)

100%

100%

0

 

 

 

 

 

5

RT Wall Pettah side(Approach portion) %

100

100

0

 

 

 

 

 

6

RT Wall Anayara side(Approach portion) %

100

100

0

 

 

       

 

 

9

RE Wall Panel Erection Pettah side(Approach portion)

400

400

0

 

 

 

 

 

10

Expansion Joint(Pettah side)

4

3

1

 

 

 

 

 

11

Expansion Joint(Anayara side)

4

3

1

 

 

 

 

 

12

Friction Slab   (Pettah side)

2

2

0

 

 

 

 

 

13

Friction Slab(Anayara side)

2

2

0

 

 

 

 

 

14

Stair Case

2

0

2

 

 

 

 

1

15

 Painting

100%

100%

0%

 

 

 

 

            

work of railway portion is progressing

 