   weekly progress as on 25.10.2013
    

 

 

 

            

Work of Railway Portion is in the scope of Railways and  which is progressing  

Sl No  Activity Description  Total Quantity Cumulative progress upto 25.10.2013 Balance  work up to 25.10.2013 Cumulative delay in Qty up to 25.10.2013 Work  planned  during the week  Actual work done during the week  Delay in Qty up to this week Work  Planned for next week 
1 SLAB Pettah side(Approach portion) 4 4 0          
2 SLAB Anayara side(Approach portion) 4 4 0          
3 Service Road Pettah side(Approach portion) 100% 100% 0          
4 Service Road Anayara side(Approach portion) 100% 100% 0          
5 RT Wall Pettah side(Approach portion) % 100 100 0          
6 RT Wall Anayara side(Approach portion) % 100 100 0                
9 RE Wall Panel Erection Pettah side(Approach portion) 400 400 0          
10 Expansion Joint(Pettah side) 4 3 1          
11 Expansion Joint(Anayara side) 4 3 1          
12 Friction Slab   (Pettah side) 2 2 0          
13 Friction Slab(Anayara side) 2 2 0          
14 Stair Case 2 0 2         1
15  Painting 100% 100% 0%                     

Work of Railway Portion is in the scope of Railways and  which is progressing

 